PRB Actions |
Return to previous page | View Schedule | PRB Decisions | Print this page |
PRB Meeting Date: 9/26/2023 | |||
Request Teleconference | Teleconference Phone #: | ||
Video Teleconference | |||
2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
9/28/2023 11:49:41 AM | Chris Rodriguez | (602) 712-4642 | 205 S 17th Ave, , |
6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
10TH AVE AT LOS ALAMOS ST | CURVE REALIGNMENT | FN1Q | ||||
9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
Yuma | 0000 | Yuma | SLS | T044201C | 0.0 | HSIPSLS-0(205)T |
16. Original Program Budget: $1,392,000 | 17. Original Program Item #: 101667 |
Project Budget | Project Budget | Project Budget |
18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
$1,392,000 | $0 (0%) | $1,392,000 |
Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
19. Current Approved: | 19a. New Project/Change Request: | 23-0009169-I |
$ 79 Item #:OTHR24 (5.7pct Local Match) FY:0 FundSRC: Desc: | $ 79 Item #:OTHR25 (5.7pct Local Match) FY:0 FundSRC: Desc: |
Current Approved | New Project/Change Request | |||
21. Fiscal Year: | 24 | 21a. Fiscal Year: | 25 | |
22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
23. Bid Adv Date: | 23a. Bid Adv Date: |
25. DESCRIPTION OF REQUEST |
Defer project. |
26. JUSTIFICATION |
New Right-of-Way and Utility relocation will be needed so the design will not be completed before the end of FY24. Project is being deferred to FY25, contingent upon HSIP Construction funding becoming available. |
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
28. OTHER ALTERNATIVES CONSIDERED |
REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
Change in FY. | Item(s) Approved. Subject to PPAC Approval. |
PRB Meeting Date: 6/20/2023 | |||
Request Teleconference | Teleconference Phone #: | ||
Video Teleconference | |||
2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
6/22/2023 9:16:35 AM | Chris Rodriguez | (602) 712-4642 | 205 S 17th Ave, , |
6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
10TH AVE AT LOS ALAMOS ST | CURVE REALIGNMENT | FN1Q | ||||
9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
Yuma | 0000 | Yuma | SLS | T044201D | 0.0 | HSIPSLS-0(205)T |
16. Original Program Budget: $30,000 | 17. Original Program Item #: 101667 |
Project Budget | Project Budget | Project Budget |
18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
$30,000 | $0 (0%) | $30,000 |
Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
19. Current Approved: | 19a. New Project/Change Request: | 23-0009169-I |
$ 28 Item #:101667 (94.3pct HSIP Funding ) FY:0 FundSRC: Desc: |
Current Approved | New Project/Change Request | |||
21. Fiscal Year: | 21a. Fiscal Year: | |||
22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
23. Bid Adv Date: | 23a. Bid Adv Date: |
25. DESCRIPTION OF REQUEST |
Establish New Project |
26. JUSTIFICATION |
Realignment of a 90-degree curve. Staff $30k |
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
28. OTHER ALTERNATIVES CONSIDERED |
REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
Establish a New Project. | Item(s) Approved. Contingent upon receipt of signed IGA and Local matching funds. |
PRB Meeting Date: 6/20/2023 | |||
Request Teleconference | Teleconference Phone #: | ||
Video Teleconference | |||
2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
6/22/2023 9:16:45 AM | Chris Rodriguez | (602) 712-4642 | 205 S 17th Ave, , |
6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
10TH AVE AT LOS ALAMOS ST | CURVE REALIGNMENT | FN1Q | ||||
9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
Yuma | 0000 | Yuma | SLS | T044203D | 0.0 | HSIPSLS-0(205)T |
16. Original Program Budget: $296,000 | 17. Original Program Item #: 101667 |
Project Budget | Project Budget | Project Budget |
18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
$296,000 | $0 (0%) | $296,000 |
Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
19. Current Approved: | 19a. New Project/Change Request: | 23-0009169-I |
$ 279 Item #:101667 (94.3pct HSIP Funding ) FY:0 FundSRC: Desc: |
Current Approved | New Project/Change Request | |||
21. Fiscal Year: | 21a. Fiscal Year: | |||
22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
23. Bid Adv Date: | 23a. Bid Adv Date: |
25. DESCRIPTION OF REQUEST |
Establish New Project |
26. JUSTIFICATION |
Realignment of a 90-degree curve. Consultant $296k |
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
28. OTHER ALTERNATIVES CONSIDERED |
REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
Establish a New Project. | Item(s) Approved. Contingent upon receipt of signed IGA and Local matching funds. |
Arizona Department of Transportation |