PRB Actions



Return to previous page | View Schedule | PRB Decisions | Print this page


PRB Meeting Date: 6/2/2026
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
6/12/2026 1:54:43 PM Judah Cain , ,
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
W Forest Dr, McLane Rd - SR 87 Road Reconstruction FM1R
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Prescott 0000 Gila PAY T074403D 0.4 PAY-0(212)
PROJECT REQUEST SUMMARY
16. Original Program Budget: $0 17. Original Program Item #: 103799
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$0 $262,000 (0%) $262,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request: 26-0011583-I
$ 15 Item #:OTHR26 ($14,934 5.7pct Local Match) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 26 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Establish New Project.
26. JUSTIFICATION
This Town of Payson project will reconstruct West Forest Drive from McLane Road to State Route 87. Proposed improvements include a new pavement structural section, sidewalks, curb and gutter, storm drains, driveways, and other related work. This subphase will be used to cover consultant design charges only. Consultant: $262K
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Establish a New Project. Item(s) Approved.


PRB Meeting Date: 6/2/2026
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
6/12/2026 1:54:20 PM Judah Cain , ,
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
W Forest Dr, McLane Rd - SR 87 Road Reconstruction FM1R
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Prescott 0000 Gila PAY T074401D 0.4 PAY-0(212)
PROJECT REQUEST SUMMARY
16. Original Program Budget: $0 17. Original Program Item #: 103799
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$0 $30,000 (0%) $30,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request: 26-0011583-I
$ 30 Item #:OTHR26 (100pct Local) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 26 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Establish New Project.
26. JUSTIFICATION
This Town of Payson project will reconstruct West Forest Drive from McLane Road to State Route 87. Proposed improvements include a new pavement structural section, sidewalks, curb and gutter, storm drains, driveways, and other related work. This subphase will be used to cover staff charges only. Staff: $30K
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Establish a New Project. Item(s) Approved.


PRB Meeting Date: 4/28/2026
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
4/30/2026 10:26:19 AM Judah Cain , ,
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
W Forest Dr, McLane Rd to SR 87 Road Reconstruction FM1R
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Prescott 0000 Gila PAY T074403D 0.4 PAY-0(212)
PROJECT REQUEST SUMMARY
16. Original Program Budget: $0 17. Original Program Item #: 103799
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$0 $262,000 (0%) $262,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request: 26-0011583-I
$ 247 Item #:103799 ($247,066 94.3pct STBGP) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 26 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Establish New Project.
26. JUSTIFICATION
This project is proposed to reconstruct the West Forest Drive road alignment from North Colcord Road to SR 87. Improvements include a new pavement structural section, sidewalks, curb and gutter, storm drains, driveways, and other related work. The authorization is contingent on collecting Local funds prior to June 30, 2026. Consultant: $262K
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Establish a New Project. Request Withdrawn.


PRB Meeting Date: 4/28/2026
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
4/30/2026 10:26:05 AM Judah Cain , ,
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
W Forest Dr, McLane Rd to SR 87 Road Reconstruction FM1R
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Prescott 0000 Gila PAY T074401D 0.4 PAY-0(212)
PROJECT REQUEST SUMMARY
16. Original Program Budget: $0 17. Original Program Item #: 103799
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$0 $30,000 (0%) $30,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request: 26-0011583-I
$ 30 Item #:OTHR26 (100pct Local) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 26 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Establish New Project.
26. JUSTIFICATION
This project is proposed to reconstruct the West Forest Drive road alignment from North Colcord Road to SR 87. Improvements include a new pavement structural section, sidewalks, curb and gutter, storm drains, driveways, and other related work. The authorization is contingent on collecting Local funds prior to June 30, 2026. Staff: $30K
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Establish a New Project. Request Withdrawn.


For Project Resource Office information or questions: PRO Mailbox