PRB Meeting Date: 10/31/2023 | |||
Request Teleconference | Teleconference Phone #: | ||
Video Teleconference | |||
2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
10/31/2023 9:32:49 AM | Chris Rodriguez | (602) 712-4642 | 205 S 17th Ave, , |
6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
AVENUE G, COUNTY 11TH ST - COUNTY 16TH ST | INSTALL RUMBLE STRIPS & WIDEN SHOULDERS | FM1Q | ||||
9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
Yuma | 0000 | Yuma | YYU | T043703D | 0.0 | HSIPYYU-0(225)T |
16. Original Program Budget: $436,000 | 17. Original Program Item #: 103648 |
Project Budget | Project Budget | Project Budget |
18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
$436,000 | $0 (0%) | $436,000 |
Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
19. Current Approved: | 19a. New Project/Change Request: | 23-0009198-I |
$ 411 Item #:103648 (94.3pct HRRR Funding) FY:0 FundSRC: Desc: |
Current Approved | New Project/Change Request | |||
21. Fiscal Year: | 21a. Fiscal Year: | |||
22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
23. Bid Adv Date: | 23a. Bid Adv Date: |
25. DESCRIPTION OF REQUEST |
Establish New Project. |
26. JUSTIFICATION |
Installation of 5 foot paved shoulders and edge line rumble strips on Avenue G from County 11th Street to County 16th Street. Consultant $436K ($410,535.00) Local Match ($24,815.00) |
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
28. OTHER ALTERNATIVES CONSIDERED |
REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
Establish a New Project. | Item(s) Approved. |
PRB Meeting Date: 10/31/2023 | |||
Request Teleconference | Teleconference Phone #: | ||
Video Teleconference | |||
2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
10/31/2023 9:30:24 AM | Chris Rodriguez | (602) 712-4642 | 205 S 17th Ave, , |
6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
AVENUE G, COUNTY 11TH ST - COUNTY 16TH ST | INSTALL RUMBLE STRIPS & WIDEN SHOULDERS | FM1Q | ||||
9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
Yuma | 0000 | Yuma | YYU | T043701D | 0.0 | HSIPYYU-0(225)T |
16. Original Program Budget: $30,000 | 17. Original Program Item #: 103648 |
Project Budget | Project Budget | Project Budget |
18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
$30,000 | $0 (0%) | $30,000 |
Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
19. Current Approved: | 19a. New Project/Change Request: | 23-0009198-I |
$ 2 Item #:OTHR24 (5.7pct Local Match) FY:0 FundSRC: Desc: |
Current Approved | New Project/Change Request | |||
21. Fiscal Year: | 21a. Fiscal Year: | |||
22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
23. Bid Adv Date: | 23a. Bid Adv Date: |
25. DESCRIPTION OF REQUEST |
Establish New Project |
26. JUSTIFICATION |
Installation of 5 foot paved shoulders and edge line rumble strips on Avenue G from County 11th Street to County 16th Street. Staff $30K ($28,290.00) Local Match ($1,710.00) |
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
28. OTHER ALTERNATIVES CONSIDERED |
REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
Establish a New Project. | Item(s) Approved. |
Arizona Department of Transportation |