PRB Actions |
Return to previous page | View Schedule | PRB Decisions | Print this page |
PRB Meeting Date: 8/22/2023 | |||
Request Teleconference | Teleconference Phone #: | ||
Video Teleconference | (602) 712-7046 | ||
2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
8/25/2023 11:01:56 AM | Tricia Brown | (602) 712-7046 | 205 S 17th Ave, , 614E |
6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
MP 288.1 - MP 289.3, BYLAS | CONSTRUCT PASSING LANE | ER1Q | ||||
9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
Safford | 70 | Graham | 288.1 | F061901D | 1.2 | 070-A(224)T |
16. Original Program Budget: $550,000 | 17. Original Program Item #: 103765 |
Project Budget | Project Budget | Project Budget |
18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
$550,000 | $0 (0%) | $550,000 |
Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
19. Current Approved: | 19a. New Project/Change Request: | |
$ 550 Item #:103765 ( ) FY:0 FundSRC: Desc: |
Current Approved | New Project/Change Request | |||
21. Fiscal Year: | 21a. Fiscal Year: | |||
22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
23. Bid Adv Date: | 23a. Bid Adv Date: |
25. DESCRIPTION OF REQUEST |
Change project name. |
26. JUSTIFICATION |
For consistency with the federal authorization, the project name will be changed to `County Rd 220 - Yellowjacket Rd, NW of Bylas`. |
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
28. OTHER ALTERNATIVES CONSIDERED |
REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
Change in Project Name/Location. | Item(s) Approved. |
PRB Meeting Date: 3/21/2023 | |||
Request Teleconference | Teleconference Phone #: | ||
Video Teleconference | (602) 712-7046 | ||
2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
3/23/2023 8:56:48 AM | Tricia Brown | (602) 712-7046 | 205 S 17th Ave, , 614E |
6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
MP 288.1 - MP 289.3, Bylas | CONSTRUCT PASSING LANE | ER1Q | ||||
9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
Safford | 70 | Graham | 288.1 | F061901D | 1.2 |
16. Original Program Budget: $0 | 17. Original Program Item #: 103765 |
Project Budget | Project Budget | Project Budget |
18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
$0 | $550,000 (0%) | $550,000 |
Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
19. Current Approved: | 19a. New Project/Change Request: | |
$ 550 Item #:70523 ( ) FY:0 FundSRC: Desc: |
Current Approved | New Project/Change Request | |||
21. Fiscal Year: | 21a. Fiscal Year: | |||
22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
23. Bid Adv Date: | 23a. Bid Adv Date: |
25. DESCRIPTION OF REQUEST |
Establish design project. |
26. JUSTIFICATION |
This is a modernization project to construct a passing lane on US 70 approximately 6 miles northwest of Bylas. This segment of US 70 was identified in the Statewide Climbing and Passing Lane Study as a priority area. This area has post-consolidation subsidence issues (clayey soils) that will need to be addressed. Construction for this project is anticipated in FY 25. Staff: $128k Consultant: $370k ICAP: $52k |
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
28. OTHER ALTERNATIVES CONSIDERED |
REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
Establish a New Project. | Item(s) Approved. Subject to PPAC Approval. |