2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
7/25/2024 11:09:30 AM | Meagan Bell | (928) 662-7990 | 1611 W JACKSON ST, , |
6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
LITTLE MORMON LAKE RD - BELL SPRING | PASSING LANES | EQ1Q | ||||
9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
Holbrook | 60 | Navajo | 345.0 | F061801C | 3.0 | 060-F(205)T |
16. Original Program Budget: $5,100,000 | 17. Original Program Item #: 103762 |
Project Budget | Project Budget | Project Budget |
18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
$5,100,000 | $306,000 (0%) | $5,406,000 |
Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
19. Current Approved: | 19a. New Project/Change Request: | |
$ 4809 Item #:103762 (CRP - $4,809,300) FY:0 FundSRC: Desc: | $ 306 Item #:70525 (CRP - $288,558 State Match - $$17,442) FY:0 FundSRC: Desc: |
Current Approved | New Project/Change Request | |||
21. Fiscal Year: | 25 | 21a. Fiscal Year: | ||
22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
23. Bid Adv Date: | 1/3/2025 | 23a. Bid Adv Date: |
25. DESCRIPTION OF REQUEST |
Increase Budget |
26. JUSTIFICATION |
Correction to printed FY25-FY29 Program. Subprogram accounts for $5.406M, however the project does not. The final program inadvertently showed $5.1M instead of $5.406M. |
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
28. OTHER ALTERNATIVES CONSIDERED |
REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
Request Withdrawn. |
PRB Meeting Date: 4/16/2024 | |||
Request Teleconference | Teleconference Phone #: | ||
Video Teleconference | |||
2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
4/19/2024 8:21:53 AM | Thomas Oreilly | (602) 712-2587 | 205 S 17th Ave, 293, 614E |
6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
LITTLE MORMON LAKE RD - BELL SPRING | PASSING LANES | EQ1Q | ||||
9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
Holbrook | 60 | Navajo | 345 | F061801D | 3 | 060-F(205)T |
16. Original Program Budget: $450,000 | 17. Original Program Item #: 103762 |
Project Budget | Project Budget | Project Budget |
18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
$450,000 | $124,000 (0%) | $574,000 |
Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
19. Current Approved: | 19a. New Project/Change Request: | |
$ 450 Item #:70523 ( ) FY:0 FundSRC: Desc: | $ 124 Item #:70524 ( ) FY:0 FundSRC: Desc: |
Current Approved | New Project/Change Request | |||
21. Fiscal Year: | 21a. Fiscal Year: | |||
22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
23. Bid Adv Date: | 23a. Bid Adv Date: |
25. DESCRIPTION OF REQUEST |
Increase budget. |
26. JUSTIFICATION |
The consultant contract exceeded the original estimate and didn`t include geotech work that will be completed by ADOT staff. Staff = $15K Consultant = $97K ICAP = $12K |
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
28. OTHER ALTERNATIVES CONSIDERED |
REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
Item(s) Approved. |
PRB Meeting Date: 3/21/2023 | |||
Request Teleconference | Teleconference Phone #: | ||
Video Teleconference | |||
2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
3/23/2023 9:35:27 AM | Thomas Oreilly | (602) 712-2587 | 205 S 17th Ave, 293, 614E |
6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
LITTLE MORMON LAKE RD - BELL SPRING | PASSING LANES | EQ1Q | ||||
9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
Holbrook | 60 | Navajo | 345 | F061801D | 3 |
16. Original Program Budget: $0 | 17. Original Program Item #: 103762 |
Project Budget | Project Budget | Project Budget |
18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
$0 | $450,000 (0%) | $450,000 |
Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
19. Current Approved: | 19a. New Project/Change Request: | |
$ 450 Item #:70523 ( ) FY:0 FundSRC: Desc: |
Current Approved | New Project/Change Request | |||
21. Fiscal Year: | 21a. Fiscal Year: | |||
22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
23. Bid Adv Date: | 23a. Bid Adv Date: |
25. DESCRIPTION OF REQUEST |
Establish design project. |
26. JUSTIFICATION |
This project will add eastbound and westbound passing lanes on US60 from MP 345 to MP 348. Construction is anticipated for FY25. Staff = $100K Consultant = $307K ICAP = $43K |
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
28. OTHER ALTERNATIVES CONSIDERED |
REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
Establish a New Project. | Item(s) Approved. Subject to PPAC Approval. |
Arizona Department of Transportation |