PRB Actions



Return to previous page | View Schedule | PRB Decisions | Print this page


PRB Meeting Date: 6/30/2026
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
7/2/2026 10:46:24 AM Allen Hathcock (602) 678-3424 , ,
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
MORNINGSTAR, 54TH, AND SPUR CROSS ROADS Pave Unpaved Alleys EP1R
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Phoenix 0000 Maricopa CVK T072101C 2.5 CVK-0(205)
PROJECT REQUEST SUMMARY
16. Original Program Budget: $1,347,000 17. Original Program Item #: 105114
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$1,347,000 $0 (0%) $1,347,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request: IGA 25-0011443-I
$ 80 Item #:OTHR27 (Local Match 5.7pct ($80,057)) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 26 21a. Fiscal Year: 27  
22. Bid Pkg Rdy Date: 8/5/2026 22a. Bid Pkg Rdy Date: 4/1/2027 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date: 4/26/2027

25. DESCRIPTION OF REQUEST
Move Project to FY27.
26. JUSTIFICATION
This request is to move Bid Advertisement to Q4 of Fiscal Year 2027. Contingent upon approval at MAG Regional Council in August.
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Change in FY. Change in Schedule. Item(s) Approved.


For Project Resource Office information or questions: PRO Mailbox

Arizona Department of Transportation