PRB Actions



Return to previous page | View Schedule | PRB Decisions | Print this page


PRB Meeting Date: 6/16/2026
Request Teleconference Teleconference Phone #:
Video Teleconference (602) 712-7046

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
6/18/2026 2:23:44 PM Tricia Brown (602) 712-7046 205 S 17TH AVE, , 614E
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
EL MIRAGE RD; SR 303 - JOMAX RD CONSTRUCT NEW ROADWAY EN1Q
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Phoenix 0000 Maricopa PEO T042801U 0.0 PEO-0(231)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $0 17. Original Program Item #: 103196
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$0 $2,050,000 (0%) $2,050,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request: 25-0011144-I
$ 528 Item #:OTHR26 (100pct Local ($528,261)) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Establish Utility Subphase.
26. JUSTIFICATION
This request is to establish the utility subphase for the El Mirage Rd extension from SR 303L to Jomax Road. The requested funds will address any utility relocations and prior rights determinations. ICAP is included in this request. This request was approved by MAG Regional Council on May 27, 2026. MAG TIP #16301 (PEO24-115URB; PEO24-115UZ)
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Establish a New Project. Request Withdrawn.


PRB Meeting Date: 6/16/2026
Request Teleconference Teleconference Phone #:
Video Teleconference (602) 712-7046

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
6/19/2026 9:50:47 AM Tricia Brown (602) 712-7046 205 S 17TH AVE, , 614E
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
EL MIRAGE RD; SR 303 - JOMAX RD CONSTRUCT NEW ROADWAY EN1Q
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Phoenix 0000 Maricopa PEO T042801R 0.0 PEO-0(231)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $0 17. Original Program Item #: 103196
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$0 $17,937,000 (0%) $17,937,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request: 25-0011144-I
$ 759 Item #:OTHR26 (Local Match 5.7pct ($758,967)) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Establish Right of Way Subphase.
26. JUSTIFICATION
This request is to establish the Right of Way subphase for the El Mirage Rd extension from SR 303L to Jomax Road. The requested funds will be used to reimburse the City of Peoria for expenses related to Right of Way acquisition. ICAP is included in this request. This request was approved by MAG Regional Council on May 27, 2026. MAG TIP #16301 (PEO24-115RRB; PEO24-115RWZ)
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Establish a New Project. Item(s) Approved.


For Project Resource Office information or questions: PRO Mailbox

Arizona Department of Transportation