4/9/2026 3:20:14 PM Skye Gentile Bush (602) 568-6782 205 S 17th Ave, 2nd Floor
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
SR 87; BIA 101 - Forest Dr & SR 260; Payson Village - Tyler Parkway Install Conduit Fiber and Adaptive Signals DY1R
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Globe 87 Gila 250.95 F090501D 2.3 999-A(650)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $0 17. Original Program Item #:
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$0 $602,000 (0%) $602,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 602 Item #:70926 (94.3 pct statewide carbon reduction 5.7 pct state match) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: FY26 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Establish�New�Project.
26. JUSTIFICATION
This project will install conduit, fiber optics, pull boxes from SR 87 (MP 250.95) to SR-87 (MP 253.25) and from SR-260 (MP 252.10) to SR-260 (MP 253.65). Install adaptive signal timing equipment as needed at the nine intersections listed below, and connect each intersection with underground fiber optics. SR 87 / BIA 101- MP 250.95 SR260 / PAYSON VILL MP-252.10 SR 87 / MAIN ST.- MP 252.04 SR260 / MANZANITA MP-252.75 SR 87 / BONITA- MP 252.23 SR260 / TYLER PRKWY MP253.65 SR 87 / SR 260 - MP 252.58 SR 87 / MALIBU DR.- MP 252.80 SR 87 / FOREST DR.- MP 253.25 Staff $66k Consultant $50lk ICAP $35k
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Establish a New Project. Item(s) Approved. Subject to PPAC Approval.