PRB Meeting Date: 9/10/2024 | |||
Request Teleconference | Teleconference Phone #: | ||
Video Teleconference | |||
2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
9/12/2024 10:30:25 AM | Trent Kelso | (602) 723-8313 | 205 S 17th Ave, 295., 614E |
6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
WELLTON-MOHAWK CANAL - IMPERIAL DAM RD | WIDENING | DX1Q | ||||
9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
Yuma | 95 | Yuma | 38.5 | F060801D | 5.6 | NFA |
16. Original Program Budget: $8,000,000 | 17. Original Program Item #: 103691 |
Project Budget | Project Budget | Project Budget |
18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
$8,000,000 | $0 (0%) | $8,000,000 |
Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
19. Current Approved: | 19a. New Project/Change Request: | |
$ 8000 Item #:DT56240 (US 95 Legislative Appropriation 2023) FY:0 FundSRC: Desc: | $ 3750 Item #:103691 (US 95 AZ Smart 2024) FY:0 FundSRC: Desc: |
Current Approved | New Project/Change Request | |||
21. Fiscal Year: | 21a. Fiscal Year: | |||
22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
23. Bid Adv Date: | 23a. Bid Adv Date: |
25. DESCRIPTION OF REQUEST |
Update funding allocations |
26. JUSTIFICATION |
Subsequent to funding the project design with legislative appropriation, the project was awarded an AZ Smart Grant totaling $3.75 million. |
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
28. OTHER ALTERNATIVES CONSIDERED |
REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
CHANGE IN BUDGET | Item(s) Approved. |
PRB Meeting Date: 1/24/2023 | |||
Request Teleconference | Teleconference Phone #: | ||
Video Teleconference | |||
2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
1/26/2023 11:30:50 AM | Trent Kelso | (602) 723-8313 | 205 S 17th Ave, 295., 614E |
6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
WELLTON-MOHAWK CANAL - IMPERIAL DAM RD | WIDENING | DX1Q | ||||
9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
Yuma | 95 | Yuma | 38.5 | F060801D | 5.6 | NFA |
16. Original Program Budget: $0 | 17. Original Program Item #: 103691 |
Project Budget | Project Budget | Project Budget |
18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
$0 | $8,000,000 (0%) | $8,000,000 |
Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
19. Current Approved: | 19a. New Project/Change Request: | |
$ 8000 Item #:DT55650 (DT55650 FY 21 Legislative Appropriation for US 95) FY:0 FundSRC: Desc: |
Current Approved | New Project/Change Request | |||
21. Fiscal Year: | 21a. Fiscal Year: | |||
22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
23. Bid Adv Date: | 23a. Bid Adv Date: |
25. DESCRIPTION OF REQUEST |
Establish New Project |
26. JUSTIFICATION |
This new project will use legislative appropriation funds reserved for the US 95 corridor. The project will consist of reconstructing US 95 from an existing 2-lane highway to a 4-lane divided highway in the vicinity of the Yuma Proving Grounds. The two directions of travel will be separated by an open median as depicted in the 2006 Design Concept Report. The project will include a preliminary design update, final design services, ROW development, Utility Coordination and an Environmental Assessment Re-Evaluation. Staff: $725K Consultant: $6,514K ICAP: $761K |
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
28. OTHER ALTERNATIVES CONSIDERED |
REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
Establish a New Project. | Item(s) Approved. |