PRB Actions



Return to previous page | View Schedule | PRB Decisions | Print this page


PRB Meeting Date: 7/23/2024
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
7/25/2024 11:08:20 AM Meagan Bell (928) 662-7990 1611 W JACKSON ST, ,
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
PAYSON TRAFFIC SIGNAL CONNECTIVITY TRAFFIC SIGNAL COMMUNICATION UPGRADE DQ1Q
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Globe 87 Gila 250.9 F060301X 4.0  
PROJECT REQUEST SUMMARY
16. Original Program Budget: $400,000 17. Original Program Item #: 103587
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$400,000 $0 (0%) $400,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 400 Item #:103587 (State 100pct) FY:0 FundSRC: Desc: $ 400 Item #:70526 (State 100pct) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 25 21a. Fiscal Year: 26  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Defer Construction to FY26.
26. JUSTIFICATION
Correction to FY25-FY29 printed program. Project was inadvertently programmed in FY25 instead of FY26.
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Change in FY. Request Withdrawn.


PRB Meeting Date: 12/20/2022
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
12/22/2022 8:05:58 AM Trevor Eltringham (928) 308-3361 6989 E 2nd St, , P899
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
Payson Traffic Signal Connectivity Traffic Signal Communication Upgrade DQ1Q
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Flagstaff 87 Gila 250.9 F060301X 4  
PROJECT REQUEST SUMMARY
16. Original Program Budget: $0 17. Original Program Item #: 103587
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$0 $151,000 (0%) $151,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 151 Item #:78823 ( ) FY:2023 FundSRC:. Desc:TSM&O  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Establish a new project
26. JUSTIFICATION
The purpose of this project is to install communication equipment to all 9 traffic signals in the town of Payson. This will allow traffic engineering and signal technician staff to connect to the signals remotely for both troubleshooting and coordination efforts to help mitigate traffic congestion. These installations will be performed by staff. ICAP is included in this request.
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Establish a New Project. Item(s) Approved. Subject to PPAC Approval.


For Project Resource Office information or questions: PRO Mailbox

Arizona Department of Transportation