| 2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
| 11/6/2025 10:52:51 AM | Olivier Mirza | , , |
| 6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
| US60 Flood Emergency Repairs | Drainage Restoration and Rehabilitation | DK1R | ||||
| 9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
| Globe | 60 | Gila | 241.0 | F089201X | 1 | |
| 16. Original Program Budget: $3,000,000 | 17. Original Program Item #: |
| Project Budget | Project Budget | Project Budget |
| 18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
| $3,000,000 | ($250,000) (0%) | $2,750,000 |
| Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
| 19. Current Approved: | 19a. New Project/Change Request: | |
| $ 3000 Item #:72226 ( ) FY:0 FundSRC: Desc: | $ -250 Item #:72226 ( ) FY:0 FundSRC: Desc: | |
| Current Approved | New Project/Change Request | |||
| 21. Fiscal Year: | 21a. Fiscal Year: | |||
| 22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
| 23. Bid Adv Date: | 23a. Bid Adv Date: | |||
| 25. DESCRIPTION OF REQUEST |
| Reduce Project Budget. |
| 26. JUSTIFICATION |
| Funding is not needed for emergency repairs. It will be used to initiate the design of the permanent drainage project. |
| 27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
| 28. OTHER ALTERNATIVES CONSIDERED |
| REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
| Item(s) Approved. |
| PRB Meeting Date: 10/21/2025 | |||
| Request Teleconference | Teleconference Phone #: | ||
| Video Teleconference | |||
| 2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
| 11/5/2025 1:47:59 PM | Olivier Mirza | , , |
| 6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
| US60 Flood Emergency Repairs | Drainage Restoration and Rehabilitation | DK1R | ||||
| 9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
| Globe | 60 | Gila | 241.0 | F089201X | 1 | |
| 16. Original Program Budget: $0 | 17. Original Program Item #: |
| Project Budget | Project Budget | Project Budget |
| 18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
| $0 | $3,000,000 (0%) | $3,000,000 |
| Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
| 19. Current Approved: | 19a. New Project/Change Request: | |
| $ 3000 Item #:72226 ( ) FY:0 FundSRC: Desc: | ||
| Current Approved | New Project/Change Request | |||
| 21. Fiscal Year: | 21a. Fiscal Year: | |||
| 22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
| 23. Bid Adv Date: | 23a. Bid Adv Date: | |||
| 25. DESCRIPTION OF REQUEST |
| Establish New Project. |
| 26. JUSTIFICATION |
| Establish a project for the emergency drainage repairs due to the recent flooding that occurred along US60 near the town of Miami. The estimate is for construction cost and includes costs for lane closures, traffic control, guardrail and transitions replacement and environmental costs. Project will be administered through Procurement. ICAP is included in this request. |
| 27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
| 28. OTHER ALTERNATIVES CONSIDERED |
| REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
| Establish a New Project. | Item(s) Approved. Subject to PPAC Approval. |