PRB Actions |
| Return to previous page | View Schedule | PRB Decisions | Print this page |
| PRB Meeting Date: 1/28/2025 | |||
| Request Teleconference | Teleconference Phone #: | ||
| Video Teleconference | |||
| 2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
| 1/30/2025 9:50:56 AM | Chris Moore | (757) 469-6679 | 205 S 17th Ave, , |
| 6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
| SANDERS & TOPOCK POE | TIRE ANOMALY SENSORS | DG1Q | ||||
| 9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
| Holbrook | 40 | Apache | 331.0 | F059401C | 1.0 | 040-E(229)T |
| 16. Original Program Budget: $260,000 | 17. Original Program Item #: 103584 |
| Project Budget | Project Budget | Project Budget |
| 18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
| $260,000 | $151,000 (0%) | $411,000 |
| Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
| 19. Current Approved: | 19a. New Project/Change Request: | |
| $ 260 Item #:103584 ( ) FY:0 FundSRC: Desc: | $ 151 Item #:74325 ( ) FY:0 FundSRC: Desc: | |
| Current Approved | New Project/Change Request | |||
| 21. Fiscal Year: | 25 | 21a. Fiscal Year: | ||
| 22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
| 23. Bid Adv Date: | 2/27/2025 | 23a. Bid Adv Date: | ||
| 25. DESCRIPTION OF REQUEST |
| Increase budget. |
| 26. JUSTIFICATION |
| This project will install tire anomaly sensors at the Sanders and Topock Ports of Entry on I-40. Request increase in budget to cover change in costs for sensors. ICAP is included in this request. |
| 27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
| 28. OTHER ALTERNATIVES CONSIDERED |
| REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
| Item(s) Approved. Subject to PPAC Approval. |
| PRB Meeting Date: 10/1/2024 | |||
| Request Teleconference | Teleconference Phone #: | ||
| Video Teleconference | |||
| 2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
| 10/3/2024 8:53:45 AM | Chris Moore | (757) 469-6679 | 205 S 17th Ave, , |
| 6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
| SANDERS & TOPOCK POE | TIRE ANOMALY SENSORS | DG1Q | ||||
| 9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
| Holbrook | 40 | Apache | 331.0 | F059401D | 1.0 | 040-E(229)T |
| 16. Original Program Budget: $30,000 | 17. Original Program Item #: 103584 |
| Project Budget | Project Budget | Project Budget |
| 18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
| $30,000 | $35,000 (0%) | $65,000 |
| Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
| 19. Current Approved: | 19a. New Project/Change Request: | |
| $ 30 Item #:74323 ( ) FY:2023 FundSRC:. Desc:PORT OF ENTRY | $ 35 Item #:74325 ( ) FY:0 FundSRC: Desc: | |
| Current Approved | New Project/Change Request | |||
| 21. Fiscal Year: | 21a. Fiscal Year: | |||
| 22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
| 23. Bid Adv Date: | 23a. Bid Adv Date: | |||
| 25. DESCRIPTION OF REQUEST |
| Increase budget. |
| 26. JUSTIFICATION |
| This project will install tire anomaly sensors at the Sanders and Topock Ports of Entry on I-40 to improve vehicle weight and safety enforcement operations. The project documents need to be converted from procurement to C&S bid package. Staff $32k ICAP $3k |
| 27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
| 28. OTHER ALTERNATIVES CONSIDERED |
| REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
| Item(s) Approved. |
| PRB Meeting Date: 9/10/2024 | |||
| Request Teleconference | Teleconference Phone #: | ||
| Video Teleconference | |||
| 2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
| 9/12/2024 10:26:45 AM | Chris Moore | (757) 469-6679 | 205 S 17th Ave, , |
| 6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
| SANDERS & TOPOCK POE | TIRE ANOMALY SENSORS | DG1Q | ||||
| 9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
| Holbrook | 40 | Apache | 331.0 | F059401X | 1.0 | 040-E(229)T |
| 16. Original Program Budget: $260,000 | 17. Original Program Item #: 103584 |
| Project Budget | Project Budget | Project Budget |
| 18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
| $260,000 | ($260,000) (0%) | $0 |
| Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
| 19. Current Approved: | 19a. New Project/Change Request: | |
| $ 260 Item #:103584 (.) FY:0 FundSRC: Desc: | $ -260 Item #:74325 ( ) FY:0 FundSRC: Desc: | |
| Current Approved | New Project/Change Request | |||
| 21. Fiscal Year: | 24 | 21a. Fiscal Year: | ||
| 22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
| 23. Bid Adv Date: | 23a. Bid Adv Date: | |||
| 25. DESCRIPTION OF REQUEST |
| Close Sub-phase |
| 26. JUSTIFICATION |
| This procurement project will be established as a C&S Bid Advertisement project. This project will install tire anomaly sensors at the Sanders and Topock Ports of Entry on I-40. |
| 27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
| 28. OTHER ALTERNATIVES CONSIDERED |
| REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
| Item(s) Approved. |
| PRB Meeting Date: 9/10/2024 | |||
| Request Teleconference | Teleconference Phone #: | ||
| Video Teleconference | |||
| 2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
| 9/12/2024 10:27:15 AM | Chris Moore | (757) 469-6679 | 205 S 17th Ave, , |
| 6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
| SANDERS & TOPOCK POE | TIRE ANOMALY SENSORS | DG1Q | ||||
| 9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
| Holbrook | 40 | Apache | 331.0 | F059401C | 1.0 | 040-E(229)T |
| 16. Original Program Budget: $0 | 17. Original Program Item #: 103584 |
| Project Budget | Project Budget | Project Budget |
| 18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
| $0 | $260,000 (0%) | $260,000 |
| Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
| 19. Current Approved: | 19a. New Project/Change Request: | |
| $ 260 Item #:74325 ( ) FY:0 FundSRC: Desc: | ||
| Current Approved | New Project/Change Request | |||
| 21. Fiscal Year: | 21a. Fiscal Year: | 25 | ||
| 22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
| 23. Bid Adv Date: | 23a. Bid Adv Date: | |||
| 25. DESCRIPTION OF REQUEST |
| Establish new project. |
| 26. JUSTIFICATION |
| This project will install tire anomaly sensors at the Sanders and Topock Ports of Entry on I-40. This was previously a Procurement Project. ICAP is included in this request. |
| 27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
| 28. OTHER ALTERNATIVES CONSIDERED |
| REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
| Establish a New Project. | Item(s) Approved. |
| PRB Meeting Date: 4/9/2024 | |||
| Request Teleconference | Teleconference Phone #: | ||
| Video Teleconference | |||
| 2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
| 4/11/2024 2:02:33 PM | Chris Moore | (757) 469-6679 | 205 S 17th Ave, , |
| 6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
| SANDERS & TOPOCK POE | TIRE ANOMALY SENSORS | DG1Q | ||||
| 9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
| Holbrook | 40 | Apache | 331.0 | F059401X | 1.0 | 040-E(229)T |
| 16. Original Program Budget: $260,000 | 17. Original Program Item #: 103584 |
| Project Budget | Project Budget | Project Budget |
| 18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
| $260,000 | $0 (0%) | $260,000 |
| Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
| 19. Current Approved: | 19a. New Project/Change Request: | |
| $ 260 Item #:103584 (.) FY:0 FundSRC: Desc: | ||
| Current Approved | New Project/Change Request | |||
| 21. Fiscal Year: | 24 | 21a. Fiscal Year: | ||
| 22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
| 23. Bid Adv Date: | 3/29/2024 | 23a. Bid Adv Date: | 5/31/2024 | |
| 25. DESCRIPTION OF REQUEST |
| Change schedule. |
| 26. JUSTIFICATION |
| This project will install tire anomaly sensors at the Sanders and Topock Ports of Entry on I-40 by procurement contract. Request to change advertisement to Q4. |
| 27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
| 28. OTHER ALTERNATIVES CONSIDERED |
| REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
| Change in Schedule. | Item(s) Approved. |
| PRB Meeting Date: 8/22/2023 | |||
| Request Teleconference | Teleconference Phone #: | ||
| Video Teleconference | |||
| 2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
| 8/25/2023 11:14:52 AM | Chris Moore | (757) 469-6679 | 205 S 17th Ave, , |
| 6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
| SANDERS & TOPOCK POE | TIRE ANOMALY SENSORS | DG1Q | ||||
| 9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
| Holbrook | 40 | Apache | 331.0 | F059401X | 1.0 | 040-E(229)T |
| 16. Original Program Budget: $200,000 | 17. Original Program Item #: 103584 |
| Project Budget | Project Budget | Project Budget |
| 18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
| $200,000 | $60,000 (0%) | $260,000 |
| Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
| 19. Current Approved: | 19a. New Project/Change Request: | |
| $ 200 Item #:103584 (.) FY:0 FundSRC: Desc: | $ 60 Item #:74324 ( ) FY:2024 FundSRC:. Desc:PORT OF ENTRY | |
| Current Approved | New Project/Change Request | |||
| 21. Fiscal Year: | 21a. Fiscal Year: | |||
| 22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
| 23. Bid Adv Date: | 23a. Bid Adv Date: | |||
| 25. DESCRIPTION OF REQUEST |
| Establish new project. |
| 26. JUSTIFICATION |
| This project will install tire anomaly sensors at the Sanders and Topock Ports of Entry on I-40 by procurement contract. ICAP is included in this request. |
| 27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
| 28. OTHER ALTERNATIVES CONSIDERED |
| REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
| Establish a New Project. | Item(s) Approved. Subject to PPAC Approval. |
| PRB Meeting Date: 12/13/2022 | |||
| Request Teleconference | Teleconference Phone #: | ||
| Video Teleconference | |||
| 2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
| 1/3/2023 7:25:58 AM | Chris Moore | (757) 469-6679 | 205 S 17th Ave, , |
| 6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
| SANDERS & TOPOCK POE | TIRE ANOMALY SENSORS | DG1Q | ||||
| 9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
| Holbrook | 40 | Apache | 331.0 | F059401D | 1.0 | 040-E(229)T |
| 16. Original Program Budget: $0 | 17. Original Program Item #: 103584 |
| Project Budget | Project Budget | Project Budget |
| 18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
| $0 | $30,000 (0%) | $30,000 |
| Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
| 19. Current Approved: | 19a. New Project/Change Request: | |
| $ 30 Item #:74323 ( ) FY:2023 FundSRC:. Desc:PORT OF ENTRY | ||
| Current Approved | New Project/Change Request | |||
| 21. Fiscal Year: | 21a. Fiscal Year: | |||
| 22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
| 23. Bid Adv Date: | 23a. Bid Adv Date: | |||
| 25. DESCRIPTION OF REQUEST |
| Establish new project. |
| 26. JUSTIFICATION |
| This project will install tire anomaly sensors at the Sanders and Topock Ports of Entry on I-40 by procurement contract to improve vehicle weight and safety enforcement operations. Staff $27k ICAP $3k |
| 27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
| 28. OTHER ALTERNATIVES CONSIDERED |
| REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
| Establish a New Project. | Item(s) Approved. Subject to PPAC Approval. |