PRB Meeting Date: 10/21/2025
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
10/24/2025 11:02:55 AM Steve Boschen 602-320-7148 , ,
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
NB I-17 Ramp to NB SR 69 Reconstruct Bridge Approach Slab DE1R
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Prescott 17 Yavapai 262 F088701D 0.1 017-A(265)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $0 17. Original Program Item #:
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$0 $250,000 (0%) $250,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 250 Item #:73326 ( ) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Establish New Project.
26. JUSTIFICATION
Bridge approach slabs have settled and rotated creating significant bumps for vehicles. Staff $205k Consultant (Env) $30k ICAP $15k
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Establish a New Project. Item(s) Approved. Subject to PPAC Approval.


For Project Resource Office information or questions: PRO Mailbox