PRB Actions |
Return to previous page | View Schedule | PRB Decisions | Print this page |
PRB Meeting Date: 5/12/2020 | |||
Request Teleconference | Teleconference Phone #: | ||
Video Teleconference | |||
2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
8/13/2020 10:06:11 AM | Lisa Pounds | (602) 712-8088 | 205 S 17th Ave, 297, 629E |
6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
I-10/US-191 SYSTEM INTERCHANGE IMPROVEMENT | Design | DA1P | ||||
9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
Safford | 10 | Cochise | 355.0 | _ | 1.0 | NFP |
16. Original Program Budget: $1,000,000 | 17. Original Program Item #: 101438 |
Project Budget | Project Budget | Project Budget |
18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
$1,000,000 | ($1,000,000) (0%) | $0 |
Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
19. Current Approved: | 19a. New Project/Change Request: | |
$ 1000 Item #:101438 ( ) FY:2020 FundSRC:. Desc:I-10/ US-191 System Interchange Improvement | $ -1000 Item #:72320 (.) FY:2020 FundSRC:. Desc:CONTINGENCY |
Current Approved | New Project/Change Request | |||
21. Fiscal Year: | 21a. Fiscal Year: | |||
22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
23. Bid Adv Date: | 23a. Bid Adv Date: |
25. DESCRIPTION OF REQUEST |
Delete Project |
26. JUSTIFICATION |
Bridge work is not required at this time. |
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
28. OTHER ALTERNATIVES CONSIDERED |
REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
Delete Project. | Item(s) Approved. Subject to PPAC Approval. |
Arizona Department of Transportation |