10/2/2025 10:50:46 AM Pei-jung Li (602) 712-8708 205 S 17th Ave, , 605E
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
Hagens Point MP 133 STABILIZE SLOPE CZ1R
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Tucson 366 Graham 133.6 F088101D 0.1  
PROJECT REQUEST SUMMARY
16. Original Program Budget: $0 17. Original Program Item #: .
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$0 $507,000 (0%) $507,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 507 Item #:73326 ( STATEWIDE MINOR PROJECTS) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Establish Design Project.
26. JUSTIFICATION
This Minor Program Project will stabilize the roadway through installation of gabion baskets, repair of pavement failures, and stabilization of slopes that eroded during storm events. The advertisement is scheduled for release in 4Q FY27. Consultant $398K Staff $80K ICAP $29K
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Change in Project Name/Location. FYI/Guidance. Item(s) Approved. Subject to PPAC Approval.


For Project Resource Office information or questions: PRO Mailbox

Arizona Department of Transportation