| 2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
| 9/18/2025 2:32:11 PM | Wang Song Shin | (602) 712-7345 | 205 S 17th Ave, , 614E |
| 6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
| OLGA FRONTAGE RD; E BUSINESS LP - 6TH ST | PAVEMENT REHABILITATION | CR1R | ||||
| 9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
| Safford | 10 | Cochise | 366.0 | F086801D | 13.0 | |
| 16. Original Program Budget: $0 | 17. Original Program Item #: . |
| Project Budget | Project Budget | Project Budget |
| 18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
| $0 | $850,000 (0%) | $850,000 |
| Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
| 19. Current Approved: | 19a. New Project/Change Request: | |
| $ 850 Item #:DT54210 (SB1737, FY26 Legislative Appropriation) FY:0 FundSRC: Desc: | ||
| Current Approved | New Project/Change Request | |||
| 21. Fiscal Year: | 21a. Fiscal Year: | |||
| 22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
| 23. Bid Adv Date: | 23a. Bid Adv Date: | |||
| 25. DESCRIPTION OF REQUEST |
| Establish new project |
| 26. JUSTIFICATION |
| This request is to establish the design phase to perform pavement rehabilitation work on Olga frontage road (the I-10 frontage road) between East business loop to 6th street. Funding for the project is by Legislative Appropriation DT54210 from SB1737. Staff $123K Consultant $678K ICAP $49K |
| 27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
| 28. OTHER ALTERNATIVES CONSIDERED |
| REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
| Establish a New Project. | Item(s) Approved. |
| Arizona Department of Transportation |