PRB Actions



Return to previous page | View Schedule | PRB Decisions | Print this page


PRB Meeting Date: 11/15/2022
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
11/17/2022 3:01:42 PM Jane Gauger (360) 712-4052
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
CALLE DE LOMA @ AZER, GILA COUNTY RAIL-HIGHWAY SAFETY UPGRADES CQ1Q
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Globe 0000 Gila 0 T003801D 0.1 GGI-0(213)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $0 17. Original Program Item #: 103570
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$0 $30,000 (0%) $30,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request: IGA 21-0008387-I
$ 30 Item #:72623 (Section 130 FHWA 100pct participation) FY:2023 FundSRC:. Desc:RAILWAY HIGHWAY CROSSING  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Establish a new project.
26. JUSTIFICATION
The project will improve safety of this rail-highway crossing by installing railroad safety upgrades at the existing Arizona Eastern Railroad (AZER) crossing (DOT 742-374E) on Calle de Loma in Gila County. Railroad Upgrades include replacing the existing asphalt surface with concrete panels, removing one track, and raising the remaining two tracks. AZER will complete the construction work. Staff will perform oversight, coordination, and clearances. Staff $30k
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Establish a New Project. Item(s) Approved. Subject to PPAC Approval.


PRB Meeting Date: 11/15/2022
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
11/17/2022 3:02:00 PM Jane Gauger (602) 712-4052
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
CALLE DE LOMA @ AZER, GILA COUNTY RAIL-HIGHWAY SAFETY UPGRADES CQ1Q
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Globe 0000 Gila 0 T003801X 0.1 GGI-0(213)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $0 17. Original Program Item #: 103570
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$0 $270,000 (0%) $270,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request: IGA 21-0008387-I
$ 270 Item #:72623 (Section 130 FHWA 100pct participation) FY:2023 FundSRC:. Desc:RAILWAY HIGHWAY CROSSING  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Establish a new project.
26. JUSTIFICATION
The project will improve safety of this rail-highway crossing by installing railroad safety upgrades at the existing Arizona Eastern Railroad (AZER) crossing (DOT 742-374E) on Calle de Loma in Gila County. Railroad upgrades include replacing the existing asphalt surface with concrete panels, removing one track, and raising the remaining two tracks. AZER will complete the construction work. 01X is Railroad Construction.
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Establish a New Project. Item(s) Approved. Subject to PPAC Approval.


For Project Resource Office information or questions: PRO Mailbox

Arizona Department of Transportation