PRB Meeting Date: 7/23/2024
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
9/10/2024 12:45:57 PM Meagan Bell (928) 662-7990 1611 W JACKSON ST, ,
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
COUNTRY CLUB RD AND KINO PKWY TIS CONSTRUCT TRAFFIC INTERCHANGES CQ1J
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Tucson 10 Pima 262.25 F054801C 2.41 NHPP-010-E(232)S
PROJECT REQUEST SUMMARY
16. Original Program Budget: $450,030,000 17. Original Program Item #: 3964
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$450,030,000 $103,605,000 (0%) $553,635,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 178023 Item #:3964 (FY24 CON) FY:2022 FundSRC:. Desc:COUNTRY CLUB ROAD TI $ 3605 Item #:103666 (Correcting Typo in 25-29 Program) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Increase Budget
26. JUSTIFICATION
Bids came in over estimate. PAG has reprogrammed funding to cover the cost increase. 1. Correct FY26 Construction amount in 5 year program, from $138,424,000 to $142,029,000. Fund $3,605,000 from 103666, PAG Unprogrammed subprogram. 2. Increase FY25 Construction funding by $9,754,000, from $133,583,000 to $143,337,000. Fund $9,616,474 from 103666, PAG Unprogrammed subprogram. Fund $137,526 from FY25 Contingency. 3. Decrease FY26 Construction funding by $23,093,000 from $142,029,000 to $118,936,000. Return funds to 103666, PAG Unprogrammed Subprogram. 4. Establish FY27 Construction funding of $113,339,000. Fund from 103666, PAG Unprogrammed subprogram.
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Item(s) Approved. Subject to PPAC Approval.


PRB Meeting Date: 7/16/2024
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
7/16/2024 9:18:53 AM Meagan Bell (928) 662-7990 1611 W JACKSON ST, ,
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
COUNTRY CLUB RD AND KINO PKWY TIS CONSTRUCT TRAFFIC INTERCHANGES CQ1J
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Tucson 10 Pima 262.25 F054801C 2.41 NHPP-010-E(232)S
PROJECT REQUEST SUMMARY
16. Original Program Budget: $450,030,000 17. Original Program Item #: 3964
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$450,030,000 $103,605,000 (0%) $553,635,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 178023 Item #:3964 (FY24 CON) FY:2022 FundSRC:. Desc:COUNTRY CLUB ROAD TI $ 3605 Item #:103666 (Correcting Typo in 25-29 Program) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Increase Budget
26. JUSTIFICATION
Bids came in over estimate. PAG has reprogrammed funding to cover the cost increase. 1. Correct FY26 Construction amount in 5 year program, from $138,424,000 to $142,029,000. Fund $3,605,000 from 103666, PAG Unprogrammed subprogram. 2. Increase FY25 Construction funding from $133,583,000 to $143,337,000. Fund $9,616,474 from 103666, PAG Unprogrammed subprogram. Fund $137,526 from FY25 Contingency. 3. Decrease FY26 Construction funding from $142,029,000 to $118,936,000. Return funds to 103666, PAG Unprogrammed Subprogram. 4. Increase FY27 Construction funding from $0 to $113,339,000. Fund from 103666, PAG Unprogrammed subprogram.
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Request Withdrawn.


PRB Meeting Date: 4/16/2024
Request Teleconference Teleconference Phone #:
Video Teleconference (602) 712-4241

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
4/19/2024 8:39:11 AM Annette Riley (602) 712-4241 205 S 17th Ave, 193, 139A
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
COUNTRY CLUB RD AND KINO PKWY TIS CONSTRUCT TRAFFIC INTERCHANGES CQ1J
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Tucson 10 Pima 264.0 F054801R 0.0 NHPP010-E(232)S
PROJECT REQUEST SUMMARY
16. Original Program Budget: $22,449,000 17. Original Program Item #: 3964
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$22,449,000 $12,611,000 (0%) $35,060,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 3049 Item #:3964 ( ) FY:2022 FundSRC:. Desc:COUNTRY CLUB ROAD TI $ 12611 Item #:3964 (.) FY:2022 FundSRC:. Desc:COUNTRY CLUB ROAD TI  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Increase budget.
26. JUSTIFICATION
These funds are needed to acquire the ROW for the construction of the project.
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Item(s) Approved.


PRB Meeting Date: 1/9/2024
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
1/12/2024 2:00:38 PM Mark Hoffman (602) 712-7454 206 S 17th Ave, 3RD F, 310B
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
COUNTRY CLUB RD AND KINO PKWY TIS CONSTRUCT TRAFFIC INTERCHANGES CQ1J
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Tucson 10 Pima 264.0 F054801C 0.0 NHPP010-E(232)S
PROJECT REQUEST SUMMARY
16. Original Program Budget: $292,330,000 17. Original Program Item #: 3964
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$292,330,000 $28,838,000 (0%) $321,168,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 10000 Item #:3694 (FY24 HURF - PAG 2.6pct) FY:0 FundSRC: Desc: $ 28838 Item #:72324 (.) FY:2024 FundSRC:. Desc:CONTINGENCY  

Current Approved New Project/Change Request  
21. Fiscal Year: 24 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Increase budget
26. JUSTIFICATION
Additional funding is needed for Construction. In FY 23, PAG project I-10, Alvernon to Valencia could not be delivered. ADOT used that funding on another project and is now restoring that funding to the PAG region in FY 2024. The Construction Funding is Programmed over FY24, FY25 and FY26. ICAP is included in this request.
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Item(s) Approved. Subject to PPAC Approval.


PRB Meeting Date: 5/23/2023
Request Teleconference Teleconference Phone #:
Video Teleconference (602) 712-7046

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
5/25/2023 9:29:45 AM Tricia Brown (602) 712-7046 205 S 17th Ave, , 614E
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
COUNTRY CLUB RD AND KINO PKWY TIS CONSTRUCT TRAFFIC INTERCHANGES CQ1J
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Tucson 10 Pima 264.0 F054801R 0.0 NHPP010-E(232)S
PROJECT REQUEST SUMMARY
16. Original Program Budget: $9,049,000 17. Original Program Item #: 3964
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$9,049,000 $13,400,000 (0%) $22,449,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 3049 Item #:3964 ( ) FY:2022 FundSRC:. Desc:COUNTRY CLUB ROAD TI $ 13400 Item #:3964 ( ) FY:2022 FundSRC:. Desc:COUNTRY CLUB ROAD TI  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Increase budget.
26. JUSTIFICATION
This request will fund the R/W acquisition and combines the Kino Parkway TI funding into one project. Environmental clearance was issued in August 2020. ICAP is included in this request.
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Item(s) Approved. Subject to PPAC Approval.


PRB Meeting Date: 5/23/2023
Request Teleconference Teleconference Phone #:
Video Teleconference (602) 712-7046

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
5/25/2023 9:27:28 AM Tricia Brown (602) 712-7046 205 S 17th Ave, , 614E
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
COUNTRY CLUB RD AND KINO PKWY TIS CONSTRUCT TRAFFIC INTERCHANGES CQ1J
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Tucson 10 Pima 264.0 F054801D 0.0 010-E(232)S
PROJECT REQUEST SUMMARY
16. Original Program Budget: $4,000,000 17. Original Program Item #: 3964
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$4,000,000 $8,000,000 (0%) $12,000,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 10000 Item #:3964 (PAG TIP ID 74.07) FY:2022 FundSRC:. Desc:COUNTRY CLUB ROAD TI $ 8000 Item #:3964 (PAG TIP ID 74.07) FY:2022 FundSRC:. Desc:COUNTRY CLUB ROAD TI  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Increase budget.
26. JUSTIFICATION
The Kino TI (PAG TIP ID 39.13) scope was previously combined with the Country Club TI project. This request aligns with the PAG funding that combined the design funding into one project. Consultant: $5000K Staff: $2300K ICAP: $700K
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Item(s) Approved. Subject to PPAC Approval.


PRB Meeting Date: 9/13/2022
Request Teleconference Teleconference Phone #:
Video Teleconference (602) 712-7046

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
9/16/2022 3:14:07 PM Tricia Brown (602) 712-7046 205 S 17th Ave, , 614E
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
COUNTRY CLUB ROAD TI CONSTRUCT TRAFFIC INTERCHANGE CQ1J
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Tucson 10 Pima 262 F054801D 3 NHPP-010-E(232)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $10,000,000 17. Original Program Item #: 3964
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$10,000,000 ($6,000,000) (0%) $4,000,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 10000 Item #:3964 (PAG TIP ID 74.07) FY:2022 FundSRC:. Desc:COUNTRY CLUB ROAD TI $ -6000 Item #:72323 ( ) FY:2023 FundSRC:. Desc:CONTINGENCY  

Current Approved New Project/Change Request  
21. Fiscal Year: 23 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Change project name. Add scope. Decrease budget.
26. JUSTIFICATION
The DCR and EA for the project corridor (I-10 and State Route 210 Study) have been completed. A Finding of No Significant Impact was issued on August 6, 2020. The project is programmed for construction in the PAG TIP in FY 2023. Country Club TI is PAG TIP ID 74.07. Kino TI is PAG TIP ID 39.13. Due to these TI`s being 1 mile apart, they will be constructed using a Design-Build delivery method as one project. The scope from Kino TI will be added to Country Club TI and the project name changed to: "Country Club Rd and Kino Pkwy TIs". Consultant: $3M Staff: $600k ICAP: $400k
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Change in Project Name/Location. Change in Scope. Item(s) Approved. Subject to PPAC Approval.


PRB Meeting Date: 9/13/2022
Request Teleconference Teleconference Phone #:
Video Teleconference (602) 712-7046

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
9/16/2022 3:20:22 PM Tricia Brown (602) 712-7046 205 S 17th Ave, , 614E
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
COUNTRY CLUB ROAD TI UTILITY RELOCATION CQ1J
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Tucson 10 Pima 262 F054801U 3 NHPP-010-E(232)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $2,640,000 17. Original Program Item #: 3964
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$2,640,000 $0 (0%) $2,640,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 2640 Item #:3964 ( ) FY:2022 FundSRC:. Desc:COUNTRY CLUB ROAD TI  

Current Approved New Project/Change Request  
21. Fiscal Year: 23 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Establish utility sub-phase.
26. JUSTIFICATION
Utility impacts and potential relocations are identified in the Final Design Concept Report, dated December 2020. Subsurface utility exploration, coordination with utility companies, prior rights determination, preparation of utility relocation plans, and potholing will be completed as part of this subphase. ICAP is included in this request.
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Establish a New Project. Item(s) Approved. Subject to PPAC Approval.


PRB Meeting Date: 9/13/2022
Request Teleconference Teleconference Phone #:
Video Teleconference (602) 712-7046

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
9/16/2022 3:19:38 PM Tricia Brown (602) 712-7046 205 S 17th Ave, , 614E
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
COUNTRY CLUB ROAD TI RIGHT OF WAY ACQUISITION CQ1J
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Tucson 10 Pima 262 F054801R 3 NHPP-010-E(232)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $3,049,000 17. Original Program Item #: 3964
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$3,049,000 $6,000,000 (0%) $9,049,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 3049 Item #:3964 ( ) FY:2022 FundSRC:. Desc:COUNTRY CLUB ROAD TI $ 6000 Item #:72323 ( ) FY:2023 FundSRC:. Desc:CONTINGENCY  

Current Approved New Project/Change Request  
21. Fiscal Year: 23 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Establish right of way sub-phase.
26. JUSTIFICATION
This request will fund the R/W acquisition. Environmental clearance was issued in August 2020. ICAP is included in this request.
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Establish a New Project. Item(s) Approved. Subject to PPAC Approval.


PRB Meeting Date: 5/25/2021
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
6/4/2021 12:25:18 PM Derek Boland (602) 712-6660 205 S 17th Ave, 295, 614E
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
COUNTRY CLUB ROAD TI RECONSTRUCT TI CQ1J
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Tucson 10 Pima _  
PROJECT REQUEST SUMMARY
16. Original Program Budget: $8,484,000 17. Original Program Item #: 3964
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$8,484,000 $49,410,000 (0%) $57,894,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 8484 Item #:3964 ( ) FY:2022 FundSRC:. Desc:COUNTRY CLUB ROAD TI $ -8484 Item #:72322 (.) FY:2022 FundSRC:. Desc:CONTINGENCY  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year: 26  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Defer Project Increase budget
26. JUSTIFICATION
This action will defer the project to FY26 and align the 5-year program with TIP rebalancing efforts, contingent upon approval by PAG regional council on May 26, 2021. Design funding for this project will be programmed for FY 2026 in the upcoming TIP amendment. There is no corresponding construction project in the program. Contingent upon PPAC Approval, this will be included in the FY22 - FY26 Five Year Program.
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Change in FY. Item(s) Approved. Subject to PPAC Approval.


PRB Meeting Date: 5/11/2021
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
5/14/2021 10:24:36 AM Derek Boland (602) 712-6660 205 S 17th Ave, 295, 614E
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
Country Club Road TI Reconstruct TI CQ1J
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Tucson 10 Pima _  
PROJECT REQUEST SUMMARY
16. Original Program Budget: $8,484,000 17. Original Program Item #: 3964
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$8,484,000 ($8,484,000) (0%) $0

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 8484 Item #:3964 ( ) FY:2022 FundSRC:. Desc:COUNTRY CLUB ROAD TI $ -8484 Item #:72322 (.) FY:2022 FundSRC:. Desc:CONTINGENCY  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year: 26  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Defer Project
26. JUSTIFICATION
This action will defer the project to FY26 and align the 5-year program with TIP rebalancing efforts, contingent upon approval by PAG regional council on May 26, 2021. Design funding for this project will be programmed for FY 2026 in the upcoming TIP amendment. This change will be reflected in the upcoming 5-yr program.
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Change in FY. Request Withdrawn. return to next meeting