PRB Actions



Return to previous page | View Schedule | PRB Decisions | Print this page


PRB Meeting Date: 10/25/2022
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
10/28/2022 10:22:30 AM Trent Kelso (602) 723-8313 205 S 17th Ave, 295., 614E
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
BORDER PATROL STA - CAMPUS DR PAVEMENT REHABILITATION CL1Q
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Tucson 90 Cochise 304.4 F059301D 16.6  
PROJECT REQUEST SUMMARY
16. Original Program Budget: $620,000 17. Original Program Item #: 103431
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$620,000 $0 (0%) $620,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 620 Item #:DT55290 (Law 2022, 2nd Regular Session, Chapter 309 (HB 2858) ) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Establish New Project
26. JUSTIFICATION
The scope of this project will include milling and replacing 16.6 miles of pavement and turnouts, replacing guardrail to MASH standards, upgrading bridge barrier and replacement deck joints, extending culverts, upgrading ADA features to current standards, and replacing signing and striping as necessary. Staff - $500K Consultant - $61K ICAP - $59K
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Establish a New Project. Item(s) Approved.


For Project Resource Office information or questions: PRO Mailbox

Arizona Department of Transportation