PRB Actions



Return to previous page | View Schedule | PRB Decisions | Print this page


PRB Meeting Date: 10/28/2025
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
11/5/2025 12:11:17 PM Pedram Shafieian (602) 712-8166 205 S 17TH AVE, , 068R
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
SR 72 & VICKSBURG RD INTERSECTION IMPROVEMENTS CI1R
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Yuma 72 La Paz 46.5 F086501D 0.4 072-A(208)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $0 17. Original Program Item #: 105956
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$0 $449,000 (0%) $449,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 449 Item #:70526 ( ) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Establish New Project.
26. JUSTIFICATION
This project is located in La Paz County along State Route 72 at Vicksburg Road, east of Bouse. The design involves widening State Route 72 in the vicinity of Vicksburg Road and adding turn lanes to separate turning vehicles from through traffic. Staff: $369K Consultant: $54K ICAP: $26K
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Establish a New Project. Item(s) Approved. Subject to PPAC Approval.


For Project Resource Office information or questions: PRO Mailbox

Arizona Department of Transportation