2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
5/1/2024 1:08:26 PM | Wesley Scatena | (602) 712-8555 | 205 S 17th Ave, , E741 |
6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
TRANSWESTERN RD - I-17 TI | VARIABLE SPEED LIMIT SIGNS & SUPPORTING ITS INFRAS | CC1P | ||||
9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
Flagstaff | 40 | Coconino | 186.0 | F028101C | 10.0 | HSIP040-C(228)T |
16. Original Program Budget: $3,000,000 | 17. Original Program Item #: 100997 |
Project Budget | Project Budget | Project Budget |
18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
$3,000,000 | $2,635,000 (0%) | $5,635,000 |
Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
19. Current Approved: | 19a. New Project/Change Request: | |
$ 2830 Item #: 100997 (94.34pct HSIP ($2,830,200)) FY:0 FundSRC: Desc: | $ 2486 Item #:70124 (94.34pct HSIP ($2,486,466)) FY:2024 FundSRC:. Desc:MODERNIZATION |
Current Approved | New Project/Change Request | |||
21. Fiscal Year: | 24 | 21a. Fiscal Year: | ||
22. Bid Pkg Rdy Date: | 5/3/2024 | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | |
23. Bid Adv Date: | 5/31/2024 | 23a. Bid Adv Date: |
25. DESCRIPTION OF REQUEST |
Increase construction budget. |
26. JUSTIFICATION |
The F0281 revised Stage IV estimate came in higher than the programmed budget. This project had been on hold since 2021. It is now being advertised with project F0499. ICAP is included in this request. |
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
28. OTHER ALTERNATIVES CONSIDERED |
REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
Item(s) Approved. Subject to PPAC Approval. |
PRB Meeting Date: 1/10/2023 | |||
Request Teleconference | Teleconference Phone #: | ||
Video Teleconference | |||
2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
1/12/2023 9:18:46 AM | Kirstin Huston | (602) 712-2167 | 205 S 17th Ave, , 121F |
6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
TRANSWESTERN RD - I-17 TI | VARIABLE SPEED LIMIT SIGNS & SUPPORTING ITS INFRAS | CC1P | ||||
9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
Flagstaff | 40 | Coconino | 186.0 | F028101C | 10.0 | 040-C(228)T |
16. Original Program Budget: $3,000,000 | 17. Original Program Item #: 100997 |
Project Budget | Project Budget | Project Budget |
18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
$3,000,000 | ($3,000,000) (0%) | $0 |
Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
19. Current Approved: | 19a. New Project/Change Request: | |
$ 3000 Item #: 100997 (Transwestern Rd - Cosnino Rd Variable Speed Limit Signs and Supporting ITS Infrastructure ) FY:0 FundSRC: Desc: | $ -170 Item #:70124 (State Match) FY:2024 FundSRC:. Desc:MODERNIZATION |
Current Approved | New Project/Change Request | |||
21. Fiscal Year: | 24 | 21a. Fiscal Year: | ||
22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
23. Bid Adv Date: | 9/1/2023 | 23a. Bid Adv Date: |
25. DESCRIPTION OF REQUEST |
Delete project. |
26. JUSTIFICATION |
Project elements will be constructed with project number F049901C: I-40 from CA State Line - Flagstaff Intelligent Transportation Systems Infrastructure(ADOT ID 103368). There will be no construction subphase associated with this project. These changes will be included in the FY24 - FY28 Five Year Program. |
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
28. OTHER ALTERNATIVES CONSIDERED |
REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
Delete Project. | Request Withdrawn. Team requested time to coordinate work with other projects |
PRB Meeting Date: 4/27/2021 | |||
Request Teleconference | Teleconference Phone #: | ||
Video Teleconference | |||
2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
6/4/2021 10:27:47 AM | Michael Andazola | (602) 712-7629 | 205 S 17th Ave, , 614E |
6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
TRANSWESTERN RD - I-17 TI | VARIABLE SPEED LIMIT SIGNS & SUPPORTING ITS INFRASTRUCTURE | CC1P | ||||
9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
Flagstaff | 40 | Coconino | 186 | F028101C | 20 | HSIP040-C(228)T |
16. Original Program Budget: $5,636,000 | 17. Original Program Item #: 100997 |
Project Budget | Project Budget | Project Budget |
18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
$5,636,000 | ($2,636,000) (0%) | $3,000,000 |
Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
19. Current Approved: | 19a. New Project/Change Request: | |
$ 5636 Item #: 100997 (Transwestern Rd - I-17 TI) FY:0 FundSRC: Desc: | $ -5636 Item #:70121 ( ) FY:2021 FundSRC:. Desc:MODERNIZATION |
Current Approved | New Project/Change Request | |||
21. Fiscal Year: | 21 | 21a. Fiscal Year: | 24 | |
22. Bid Pkg Rdy Date: | 2/26/2021 | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | |
23. Bid Adv Date: | 3/31/2021 | 23a. Bid Adv Date: |
25. DESCRIPTION OF REQUEST |
Defer project, decrease budget. |
26. JUSTIFICATION |
In order to accomodate the upcoming I-40 West Broadband Corridor project, this project is being deferred to FY24. Programmed funding for this project will be utilized for other projects in FY21. |
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
28. OTHER ALTERNATIVES CONSIDERED |
REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
Change in FY. Change in Scope. | Item(s) Approved. Subject to PPAC Approval. |
PRB Meeting Date: 4/20/2021 | |||
Request Teleconference | Teleconference Phone #: | ||
Video Teleconference | |||
2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
4/21/2021 8:55:43 AM | Michael Andazola | (602) 712-7629 | 205 S 17th Ave, , 614E |
6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
TRANSWESTERN RD - I-17 TI | VARIABLE SPEED LIMIT SIGNS & SUPPORTING ITS INFRASTRUCTURE | CC1P | ||||
9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
Flagstaff | 40 | Coconino | 186 | F028101C | 20 | HSIP040-C(228)T |
16. Original Program Budget: $5,636,000 | 17. Original Program Item #: 100997 |
Project Budget | Project Budget | Project Budget |
18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
$5,636,000 | $258,000 (0%) | $5,894,000 |
Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
19. Current Approved: | 19a. New Project/Change Request: | |
$ 5636 Item #: 100997 (Transwestern Rd - I-17 TI) FY:0 FundSRC: Desc: | $ 258 Item #:79921 ( ) FY:0 FundSRC: Desc: |
Current Approved | New Project/Change Request | |||
21. Fiscal Year: | 21 | 21a. Fiscal Year: | ||
22. Bid Pkg Rdy Date: | 2/26/2021 | 22a. Bid Pkg Rdy Date: | 3/31/2021 | 24. Verified all of the new funding sources |
23. Bid Adv Date: | 3/31/2021 | 23a. Bid Adv Date: | 5/30/2021 |
25. DESCRIPTION OF REQUEST |
Increase budget, change schedule. |
26. JUSTIFICATION |
The original HSIP estimate underestimated the construction costs for 144 fiber and 7-way multi-duct conduit and the software development. Additional funding is required to account for increases in unit prices for fiber optic cable and conduit as well as account for costs of software development for integration of the road weather system components. ICAP is included in this request. Project is moving to 4th qtr advertisement. |
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
28. OTHER ALTERNATIVES CONSIDERED |
REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
Change in Schedule. | Request Withdrawn. Project may be pushed out to future FY. |
PRB Meeting Date: 3/30/2021 | |||
Request Teleconference | Teleconference Phone #: | ||
Video Teleconference | |||
2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
4/6/2021 2:22:36 PM | Michael Andazola | (602) 712-7629 | 205 S 17th Ave, , 614E |
6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
TRANSWESTERN RD - I-17 TI | VARIABLE SPEED LIMIT SIGNS & SUPPORTING ITS INFRASTRUCTURE | CC1P | ||||
9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
Flagstaff | 40 | Coconino | 186 | F028101C | 20 | HSIP040-C(228)T |
16. Original Program Budget: $5,636,000 | 17. Original Program Item #: 100997 |
Project Budget | Project Budget | Project Budget |
18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
$5,636,000 | $0 (0%) | $5,636,000 |
Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
19. Current Approved: | 19a. New Project/Change Request: | |
$ 5636 Item #: 100997 (Transwestern Rd - I-17 TI) FY:0 FundSRC: Desc: |
Current Approved | New Project/Change Request | |||
21. Fiscal Year: | 21 | 21a. Fiscal Year: | ||
22. Bid Pkg Rdy Date: | 2/26/2021 | 22a. Bid Pkg Rdy Date: | 3/31/2021 | 24. Verified all of the new funding sources |
23. Bid Adv Date: | 3/31/2021 | 23a. Bid Adv Date: | 5/30/2021 |
25. DESCRIPTION OF REQUEST |
Change Schedule |
26. JUSTIFICATION |
The bid advertisement date is being pushed to the 4th Qtr due to delays with environmental cultural consultation required for Environmental Clearance. |
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
28. OTHER ALTERNATIVES CONSIDERED |
REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
Change in Schedule. | Item(s) Approved. |
PRB Meeting Date: 3/30/2021 | |||
Request Teleconference | Teleconference Phone #: | ||
Video Teleconference | |||
2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
4/6/2021 2:22:15 PM | Michael Andazola | (602) 712-7629 | 205 S 17th Ave, , 614E |
6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
TRANSWESTERN RD - I-17 TI | VARIABLE SPEED LIMIT SIGNS & SUPPORTING ITS INFRASTRUCTURE | CC1P | ||||
9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
Flagstaff | 40 | Coconino | 186 | F028101U | 20 | HSIP040-C(228)T |
16. Original Program Budget: $0 | 17. Original Program Item #: 100997 |
Project Budget | Project Budget | Project Budget |
18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
$0 | $28,000 (0%) | $28,000 |
Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
19. Current Approved: | 19a. New Project/Change Request: | |
$ 28 Item #:70121 (APS Utility Agreement) FY:2021 FundSRC:. Desc:MODERNIZATION |
Current Approved | New Project/Change Request | |||
21. Fiscal Year: | 21a. Fiscal Year: | |||
22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
23. Bid Adv Date: | 23a. Bid Adv Date: |
25. DESCRIPTION OF REQUEST |
Establish utility subphase |
26. JUSTIFICATION |
Funding is needed to compensate APS for the costs to provide electrical service from outside ADOT right of way to the point of service within the project limits. APS Agreement: $25K ICAP: $3K |
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
28. OTHER ALTERNATIVES CONSIDERED |
REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
Establish a New Project. | Item(s) Approved. |
PRB Meeting Date: 10/20/2020 | |||
Request Teleconference | Teleconference Phone #: | ||
Video Teleconference | |||
2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
1/13/2021 7:54:21 AM | Michael Andazola | (602) 712-7629 | 205 S 17th Ave, , 614E |
6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
TRANSWESTERN RD - COSNINO RD | VARIABLE SPEED LIMIT SIGNS & SUPPORTING ITS INFRASTRUCTURE | CC1P | ||||
9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
Flagstaff | 40 | Coconino | 186 | F028101D | 20 | HSIP040-C(228)T |
16. Original Program Budget: $563,000 | 17. Original Program Item #: 100997 |
Project Budget | Project Budget | Project Budget |
18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
$563,000 | $74,000 (0%) | $637,000 |
Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
19. Current Approved: | 19a. New Project/Change Request: | |
$ 107 Item #:70120 (.) FY:2020 FundSRC:. Desc:MODERNIZATION | $ 74 Item #:70121 ( ) FY:2021 FundSRC:. Desc:MODERNIZATION |
Current Approved | New Project/Change Request | |||
21. Fiscal Year: | 21a. Fiscal Year: | |||
22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
23. Bid Adv Date: | 23a. Bid Adv Date: |
25. DESCRIPTION OF REQUEST |
Increase design budget,Change scope, Change Project Name |
26. JUSTIFICATION |
To stay within the programmed construction budget,the project length was reduced from a 20 mile length (Transwestern Rd to Cosnino Rd) to a 10 mile length (Transwestern Rd to I-17 TI). Change project name to: "Transwestern Rd - I-17 TI". The additional funding is required to cover railroad permit costs to BNSF for installation of fiber optic conduit attached to the bridge barrier at the eastbound overpass bridge (No. 322, MP 190.8 - MP 190.9) crossing over the railroad right of way. This cost was not anticipated during the development of the original design budget. Additional funding is needed for the cultural monitoring plan that was also not part of the original design budget. BNSF Permit $33K Monitoring Plan $34K ICAP $7K |
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
28. OTHER ALTERNATIVES CONSIDERED |
REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
Change in Project Name/Location. Change in Scope. | Item(s) Approved. Subject to PPAC Approval. |
PRB Meeting Date: 5/5/2020 | |||
Request Teleconference | Teleconference Phone #: | ||
Video Teleconference | |||
2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
5/12/2020 9:43:05 AM | Michael Andazola | (602) 712-7629 | 205 S 17th Ave, , 614E |
6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
TRANSWESTERN RD - COSNINO RD | VARIABLE SPEED LIMIT SIGNS & SUPPORTING ITS INFRASTRUCTURE | CC1P | ||||
9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
Flagstaff | 40 | Coconino | 186 | F028101D | 20 | HSIP040-C(228)T |
16. Original Program Budget: $469,000 | 17. Original Program Item #: 100997 |
Project Budget | Project Budget | Project Budget |
18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
$469,000 | $94,000 (0%) | $563,000 |
Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
19. Current Approved: | 19a. New Project/Change Request: | |
$ 362 Item #:100997. (Transwestern Rd - Cosnino Rd Varible Speed Limit Signs and Supporting ITS Infrastructure) FY:0 FundSRC: Desc: | $ 94 Item #:70120 ( ) FY:2020 FundSRC:. Desc:MODERNIZATION |
Current Approved | New Project/Change Request | |||
21. Fiscal Year: | 21a. Fiscal Year: | |||
22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
23. Bid Adv Date: | 23a. Bid Adv Date: |
25. DESCRIPTION OF REQUEST |
Increase budget. |
26. JUSTIFICATION |
ADOT personnel were originally scheduled to perform the cultural survey. However when the scope of work and clearance limits were fully understood, it was determined it was beyond what could be handled in-house, due to the fact that the additional areas require a higher level of analysis and field work. In order to maintain the project delivery schedule, a sub-consultant was added to complete the work. Consultant $81k Staff $4k ICAP $9k |
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
28. OTHER ALTERNATIVES CONSIDERED |
REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
Item(s) Approved. |
PRB Meeting Date: 12/10/2019 | |||
Request Teleconference | Teleconference Phone #: | ||
Video Teleconference | |||
2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
12/16/2019 9:10:09 AM | Michael Andazola | (602) 712-7629 | 205 S 17th Ave, , 614E |
6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
TRANSWESTERN RD - COSNINO RD | VARIABLE SPEED LIMIT SIGNS & SUPPORTING ITS INFRASTRUCTURE | CC1P | ||||
9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
Flagstaff | 40 | Coconino | 186 | F028101D | 20 | HSIP040-C(228)T |
16. Original Program Budget: $362,000 | 17. Original Program Item #: 100997 |
Project Budget | Project Budget | Project Budget |
18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
$362,000 | $107,000 (0%) | $469,000 |
Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
19. Current Approved: | 19a. New Project/Change Request: | |
$ 362 Item #:100997. (Transwestern Rd - Cosnino Rd Varible Speed Limit Signs and Supporting ITS Infrastructure) FY:0 FundSRC: Desc: | $ 107 Item #:70120 ( ) FY:2020 FundSRC:. Desc:MODERNIZATION |
Current Approved | New Project/Change Request | |||
21. Fiscal Year: | 21a. Fiscal Year: | |||
22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
23. Bid Adv Date: | 23a. Bid Adv Date: |
25. DESCRIPTION OF REQUEST |
Increase budget. |
26. JUSTIFICATION |
Funding is needed to cover the development of a Concept of Operations describing the purpose of the proposed system and a Communications Plan, identifying options for device communications back to the ADOT TOC. Both of these will recommend the ITS components needed for the project. The Break Down of Costs is as follows: Consultant $97k ICAP $10k |
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
28. OTHER ALTERNATIVES CONSIDERED |
REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
Item(s) Approved. |
PRB Meeting Date: 8/6/2019 | |||
Request Teleconference | Teleconference Phone #: | ||
Video Teleconference | |||
2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
8/21/2019 10:36:44 AM | Michael Andazola | (602) 712-7629 | 205 S 17th Ave, , 614E |
6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
TRANSWESTERN RD - COSNINO RD | VARIABLE SPEED LIMIT SIGNS & OPERATIONS EQUIPMENT | CC1P | ||||
9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
Flagstaff | 40 | Coconino | 186 | F028101D | 20 | HSIP040-C(228)T |
16. Original Program Budget: $362,000 | 17. Original Program Item #: 100997 |
Project Budget | Project Budget | Project Budget |
18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
$362,000 | $0 (0%) | $362,000 |
Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
19. Current Approved: | 19a. New Project/Change Request: | |
$ 362 Item #:100997 ( ) FY:2020 FundSRC:. Desc:Transwestern Rd - Cosnino Rd |
Current Approved | New Project/Change Request | |||
21. Fiscal Year: | 21a. Fiscal Year: | |||
22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
23. Bid Adv Date: | 23a. Bid Adv Date: |
25. DESCRIPTION OF REQUEST |
Establish Project |
26. JUSTIFICATION |
This HISP project will install 20 variable speed limit signs and operations equipment on I-40. Staff $82K Consultant $247K ICAP $33K |
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
28. OTHER ALTERNATIVES CONSIDERED |
REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
Establish a New Project. | Item(s) Approved. |
Arizona Department of Transportation |