PRB Actions



Return to previous page | View Schedule | PRB Decisions | Print this page


PRB Meeting Date: 5/14/2024
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
5/16/2024 10:13:47 AM Rehnuma Rahman (602) 712-7342 205 S 17th Ave, Next, O68R
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
I-10 - CITY OF MARICOPA WIDENING BT1Q
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Phoenix 347 Pinal 175.7 F058101D 13.4 347-A(214)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $5,900,000 17. Original Program Item #: 103478
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$5,900,000 $80,000 (0%) $5,980,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 5900 Item #:103478 (HB 2858, DT55370) FY:0 FundSRC: Desc: $ 80 Item #:72324 (HB 2858) FY:2024 FundSRC:. Desc:CONTINGENCY  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Increase budget.
26. JUSTIFICATION
Additional funding is needed to complete the consultant related environmental, right of way and utility tasks. This project is a Legislative Appropriation project from HB 2858. Consultant $72K ICAP $8K Contingent upon approval by MAG Regional Council
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Item(s) Approved.


PRB Meeting Date: 5/14/2024
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
5/16/2024 10:13:13 AM Rehnuma Rahman (602) 712-7342 205 S 17th Ave, Next, O68R
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
I-10 - CITY OF MARICOPA WIDENING BT1Q
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Phoenix 347 Pinal 175.7 F058101L 13.4 347-A(214)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $100,000 17. Original Program Item #: 103478
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$100,000 ($80,000) (0%) $20,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 100 Item #:72323 (From HB 2858 ) FY:2023 FundSRC:. Desc:CONTINGENCY $ -80 Item #:72324 (HB 2858) FY:2024 FundSRC:. Desc:CONTINGENCY  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Decrease funding.
26. JUSTIFICATION
This request is to reduce the budget for this project. This funding is no longer needed as the RSA has been completed for the 01L phase. This project is a Legislative Appropriation project from HB 2858. Contingent upon approval by MAG Regional Council.
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Item(s) Approved.


PRB Meeting Date: 1/31/2023
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
5/13/2024 7:28:00 AM Rehnuma Rahman (602) 712-7342 205 S 17th Ave, Next, O68R
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
I-10 - CITY OF MARICOPA WIDENING BT1Q
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Phoenix 347 Pinal 175.7 F058101D 13.4 347-A(214)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $6,000,000 17. Original Program Item #: 103478
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$6,000,000 ($100,000) (0%) $5,900,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 6000 Item #:DT55370 (HB 2858 ) FY:0 FundSRC: Desc: $ -100 Item #:72323 (For RSA) FY:2023 FundSRC:. Desc:CONTINGENCY  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Decrease budget.
26. JUSTIFICATION
This request is to transfer the funding for the TSMO staff to charge to perform a Roadway Safety Assessment. This project is a Legislative Appropriation project from HB 2858.
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Item(s) Approved.


PRB Meeting Date: 1/31/2023
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
2/2/2023 1:35:46 PM Rehnuma Rahman (602) 712-7342 205 S 17th Ave, Next, O68R
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
I-10 - CITY OF MARICOPA WIDENING BT1Q
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Phoenix 347 Pinal 175.7 F058101L 13.4 347-A(214)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $0 17. Original Program Item #: 103478
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$0 $100,000 (0%) $100,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 100 Item #:72323 (For RSA F0581) FY:2023 FundSRC:. Desc:CONTINGENCY  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Establish new project.
26. JUSTIFICATION
This request is for staff to perform a Roadway Safety Assessment. This project is a Legislative Appropriation project from HB 2858. Staff: $100K
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Establish a New Project. Item(s) Approved.


PRB Meeting Date: 10/25/2022
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
10/28/2022 9:44:59 AM Rehnuma Rahman (602) 712-7342 205 S 17th Ave, Next, O68R
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
I-10 - CITY OF MARICOPA WIDENING BT1Q
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Phoenix 347 Pinal 175.7 F058101R 13.4 347-A(214)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $0 17. Original Program Item #: 103478
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$0 $111,000 (0%) $111,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 111 Item #:DT55370 (.) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Establish new project.
26. JUSTIFICATION
The property acquisition is required at the three intersections and the I-10 and SR347 interchange within the project limits. This project is Legislative Appropriation project from HB 2858. Acquisition: $100K ICAP:$11K
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Establish a New Project. Request Withdrawn. Included in 01D phase request.


PRB Meeting Date: 10/25/2022
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
10/28/2022 9:44:39 AM Rehnuma Rahman (602) 712-7342 205 S 17th Ave, Next, O68R
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
I-10 - CITY OF MARICOPA WIDENING BT1Q
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Phoenix 347 Pinal 175.7 F058101D 13.4 347-A(214)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $6,000,000 17. Original Program Item #: 103478
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$6,000,000 $0 (0%) $6,000,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 6000 Item #:DT55370 (HB 2858 ) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Establish new project.
26. JUSTIFICATION
This project is widening the SR 347 from two lanes to three lanes in each direction. The survey will be performed by ADOT staff. This project is Legislative Appropriation project from HB 2858. Staff: $416K Consultant:$5,013K ICAP:$571K
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Establish a New Project. Item(s) Approved. Contingent upon approval by MAG Regional Council on 11/30/2022.


For Project Resource Office information or questions: PRO Mailbox

Arizona Department of Transportation