PRB Actions |
| Return to previous page | View Schedule | PRB Decisions | Print this page |
| PRB Meeting Date: 7/14/2026 | |||
| Request Teleconference | Teleconference Phone #: | ||
| Video Teleconference | |||
| 2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
| 7/20/2026 8:43:33 AM | Patrick O`Leske | (602) 568-3357 | 205 S 17TH AVE, , |
| 6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
| ELLSWORTH RD - MERIDIAN RD | FREEWAY WIDENING - GPL | BR1R | ||||
| 9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
| Phoenix | 60 | Maricopa | 190.0 | F083001D | 0.0 | 060-C(224)T |
| 16. Original Program Budget: $4,433,000 | 17. Original Program Item #: 105490 |
| Project Budget | Project Budget | Project Budget |
| 18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
| $4,433,000 | $0 (0%) | $4,433,000 |
| Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
| 19. Current Approved: | 19a. New Project/Change Request: | |
| $ 2216 Item #:105490 (NHPP ($2,216,391)) FY:0 FundSRC: Desc: | ||
| Current Approved | New Project/Change Request | |||
| 21. Fiscal Year: | 27 | 21a. Fiscal Year: | ||
| 22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
| 23. Bid Adv Date: | 23a. Bid Adv Date: | |||
| 25. DESCRIPTION OF REQUEST |
| Establish New Project. |
| 26. JUSTIFICATION |
| This request is to establish the 01D subphase of this project for design. The proposed improvements include widening US-60 between Ellsworth Rd and Meridian Rd by adding an additional general-purpose lane in each direction. Anticipated work also includes the widening of existing structures to accommodate new lanes, construction of sound/noise walls where applicable, and possible utility relocation efforts. MAG TIP ID 33075/27-512D Consultant - $3,850k ADOT Staff - $328k ICAP - $255k |
| 27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
| 28. OTHER ALTERNATIVES CONSIDERED |
| REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
| Establish a New Project. | Item(s) Approved. |
| PRB Meeting Date: 3/24/2026 | |||
| Request Teleconference | Teleconference Phone #: | ||
| Video Teleconference | |||
| 2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
| 3/31/2026 11:40:13 AM | Patrick O`leske | (602) 568-3357 | 205 S 17TH AVE |
| 6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
| ELLSWORTH RD - MERIDIAN RD | FREEWAY WIDENING - GPL | BR1R | ||||
| 9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
| Phoenix | 60 | Maricopa | 190.0 | F083001L | 3.0 | 060-C(224)T |
| 16. Original Program Budget: $3,501,000 | 17. Original Program Item #: 105490 |
| Project Budget | Project Budget | Project Budget |
| 18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
| $3,501,000 | $0 (0%) | $3,501,000 |
| Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
| 19. Current Approved: | 19a. New Project/Change Request: | |
| $ 1333 Item #:105500 (100pct RARF ($1,333,486)) FY:0 FundSRC: Desc: | ||
| Current Approved | New Project/Change Request | |||
| 21. Fiscal Year: | 21a. Fiscal Year: | |||
| 22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
| 23. Bid Adv Date: | 23a. Bid Adv Date: | |||
| 25. DESCRIPTION OF REQUEST |
| Establish New Project. |
| 26. JUSTIFICATION |
| This request is to establish the 01L subphase for the Ellsworth Rd to Meridian Rd GPL project. The requested funds will be utilized to update the DCR previously completed under H8665 in 2018. MAG TIP ID DOT26-515D/DOT26-516D. Consultant - $3001k ADOT Staff - $299k ICAP - $201k |
| 27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
| 28. OTHER ALTERNATIVES CONSIDERED |
| REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
| Establish a New Project. | Item(s) Approved. |
| Arizona Department of Transportation |