9/1/2022 1:25:08 PM Carlos Lopez (602) 712-4786 1611 W Jackson St
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
I-11; I-10 - US 93 DCR + Tier 2 EIS BP1Q
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Phoenix 11 Maricopa F054301L 55  
PROJECT REQUEST SUMMARY
16. Original Program Budget: $25,000,000 17. Original Program Item #: 5521
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$25,000,000 $0 (0%) $25,000,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 25000 Item #:DT55440 (Legislative Appropriation) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Establish a new project
26. JUSTIFICATION
The I-11 Tier 1 Study between Nogales and Wickenburg was completed in 2021. House Bill 2858 allocated funds for an I-11 Tier 2 (DCR/NEPA) study between 1-10 and US 93. Consultant - $22M Staff - $500K ICAP - $2.5M
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Establish a New Project. Item(s) Approved.