PRB Actions



Return to previous page | View Schedule | PRB Decisions | Print this page


PRB Meeting Date: 8/30/2022
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
9/1/2022 1:24:43 PM Sam Patton 602-712-6168 1611 W Jackson St
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
Sonoran Corridor (SR 410) DCR + TIER 2 EIS BO1Q
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Tucson SR 410 Pima F054101L 20.4  
PROJECT REQUEST SUMMARY
16. Original Program Budget: $14,000,000 17. Original Program Item #: 103418
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$14,000,000 $0 (0%) $14,000,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 14000 Item #:DT55430 (Legislative Appropriation from House Bill 2858 ) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Establish a new project
26. JUSTIFICATION
The Sonoran Corridor Tier 1 study was completed and determined a preferred corridor. This DCR and Environmental (Tier 2) will be the next step toward the construction of the new Sonoran Corridor. This study will determine an alignment for the Sonoran Corridor (SR 410). The study will consider physical and environmental concerns in the development of that alignment. The information from this study will provide for the future construction of the Sonoran Corridor (SR 410). Once constructed the Sonoran Corridor (SR410) will reduce congestion on the surrounding area road systems, provide road system to system linkages and accommodate future travel demands. Staff - $400K Consultant - $12.2M ICAP - $1.4M
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Establish a New Project. Item(s) Approved.


For Project Resource Office information or questions: PRO Mailbox

Arizona Department of Transportation