PRB Actions |
| Return to previous page | View Schedule | PRB Decisions | Print this page |
| PRB Meeting Date: 11/17/2026 | |||
| Request Teleconference | Teleconference Phone #: | ||
| Video Teleconference | (602) 712-7046 | ||
| 2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
| 11/19/2026 2:56:07 PM | Tricia Brown | (602) 712-7046 | 205 S 17TH AVE, , 614E |
| 6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
| SR 303L - ESTRELLA PKWY | CONSTRUCT NEW FREEWAY | BK1R | ||||
| 9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
| Phoenix | 30 | Maricopa | 100.0 | F086001U | 0.0 | 030-C(003)T |
| 16. Original Program Budget: $21,220,000 | 17. Original Program Item #: 104980 |
| Project Budget | Project Budget | Project Budget |
| 18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
| $21,220,000 | $0 (0%) | $21,220,000 |
| Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
| 19. Current Approved: | 19a. New Project/Change Request: | |
| $ 21220 Item #:104980 ($21,220,000 Prop 479 RARF 100pct) FY:0 FundSRC: Desc: | ||
| Current Approved | New Project/Change Request | |||
| 21. Fiscal Year: | 32 | 21a. Fiscal Year: | ||
| 22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
| 23. Bid Adv Date: | 6/30/2032 | 23a. Bid Adv Date: | ||
| 25. DESCRIPTION OF REQUEST |
| Establish utility project. |
| 26. JUSTIFICATION |
| This request will fund utility relocations needed to move existing Buckeye Water Conservation and Drainage District, and Roosevelt Irrigation District facilities outside of the proposed roadway limits. ICAP is included in this request. MAG TIP ID DOT26-513R |
| 27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
| 28. OTHER ALTERNATIVES CONSIDERED |
| REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
| Establish a New Project. | Item(s) Approved. |
| PRB Meeting Date: 10/20/2026 | |||
| Request Teleconference | Teleconference Phone #: | ||
| Video Teleconference | (602) 712-7046 | ||
| 2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
| 10/26/2026 1:58:08 PM | Tricia Brown | (602) 712-7046 | 205 S 17TH AVE, , 614E |
| 6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
| SR 303L - ESTRELLA PKWY | CONSTRUCT NEW FREEWAY | BK1R | ||||
| 9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
| Phoenix | 30 | Maricopa | 100.0 | F086001U | 0.0 | 030-C(003)T |
| 16. Original Program Budget: $68,965,000,000 | 17. Original Program Item #: 104980 |
| Project Budget | Project Budget | Project Budget |
| 18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
| $68,965,000,000 | $0 (0%) | $68,965,000,000 |
| Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
| 19. Current Approved: | 19a. New Project/Change Request: | |
| $ 48276 Item #:104980 ($48,275,500 Prop 479 RARF 100pct) FY:0 FundSRC: Desc: | ||
| Current Approved | New Project/Change Request | |||
| 21. Fiscal Year: | 32 | 21a. Fiscal Year: | ||
| 22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
| 23. Bid Adv Date: | 6/30/2032 | 23a. Bid Adv Date: | ||
| 25. DESCRIPTION OF REQUEST |
| Establish utility project. |
| 26. JUSTIFICATION |
| This request will fund utility relocations needed to move existing Western Area Power Administration, Arizona Public Service, Salt River Project, Buckeye Water Conservation and Drainage District, and Roosevelt Irrigation District facilities outside of the proposed roadway limits. MAG TIP ID DOT26-513R |
| 27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
| 28. OTHER ALTERNATIVES CONSIDERED |
| REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
| Establish a New Project. | Request Withdrawn. |
| PRB Meeting Date: 10/20/2026 | |||
| Request Teleconference | Teleconference Phone #: | ||
| Video Teleconference | (602) 712-7046 | ||
| 2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
| 10/26/2026 1:48:59 PM | Tricia Brown | (602) 712-7046 | 205 S 17TH AVE, , 614E |
| 6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
| SR 303L - ESTRELLA PKWY | CONSTRUCT NEW FREEWAY | BK1R | ||||
| 9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
| Phoenix | 30 | Maricopa | 100.0 | F086001R | 0.0 | 030-C(003)T |
| 16. Original Program Budget: $22,380,000 | 17. Original Program Item #: 104980 |
| Project Budget | Project Budget | Project Budget |
| 18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
| $22,380,000 | $0 (0%) | $22,380,000 |
| Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
| 19. Current Approved: | 19a. New Project/Change Request: | |
| $ 6714 Item #:104980 ($6,714,099.60 NHPP) FY:0 FundSRC: Desc: | ||
| Current Approved | New Project/Change Request | |||
| 21. Fiscal Year: | 32 | 21a. Fiscal Year: | ||
| 22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
| 23. Bid Adv Date: | 6/30/2032 | 23a. Bid Adv Date: | ||
| 25. DESCRIPTION OF REQUEST |
| Establish right of way project. |
| 26. JUSTIFICATION |
| This request will fund the acquisition of permanent right of way and easements needed for utility relocations. ICAP is included. Environmental clearance was issued in November 2018 for H6870 and in November 2019 for H6876. MAG TIP ID DOT26-513R |
| 27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
| 28. OTHER ALTERNATIVES CONSIDERED |
| REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
| Establish a New Project. | Request Withdrawn. |
| PRB Meeting Date: 4/21/2026 | |||
| Request Teleconference | Teleconference Phone #: | ||
| Video Teleconference | (602) 712-7046 | ||
| 2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
| 5/12/2026 10:30:15 AM | Tricia Brown | (602) 712-7046 | 205 S 17TH AVE, , 614E |
| 6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
| SR 303L - ESTRELLA PKWY | CONSTRUCT NEW FREEWAY | BK1R | ||||
| 9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
| Phoenix | 30 | Maricopa | 0.0 | F086001R | 0.0 | 030-C(003)T |
| 16. Original Program Budget: $88,470,000 | 17. Original Program Item #: 104980 |
| Project Budget | Project Budget | Project Budget |
| 18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
| $88,470,000 | $0 (0%) | $88,470,000 |
| Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
| 19. Current Approved: | 19a. New Project/Change Request: | |
| $ 68776 Item #:104980 (NHPP $68,776,045) FY:0 FundSRC: Desc: | $ -19694 Item #:49926 (RARF ($19,694,011)) FY:0 FundSRC: Desc: | |
| Current Approved | New Project/Change Request | |||
| 21. Fiscal Year: | 26 | 21a. Fiscal Year: | 27 | |
| 22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
| 23. Bid Adv Date: | 23a. Bid Adv Date: | |||
| 25. DESCRIPTION OF REQUEST |
| Defer to FY 2027. |
| 26. JUSTIFICATION |
| This project was kicked off for final design in March 2026 and additional time is needed to determine the right of way and utility relocation limits which will extend beyond the end of this fiscal year. This request is contingent on MAG Regional Council approval in May 2026. MAG TIP ID DOT26-513R |
| 27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
| 28. OTHER ALTERNATIVES CONSIDERED |
| REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
| Establish a New Project. | Item(s) Approved. Subject to PPAC Approval. |
| PRB Meeting Date: 9/23/2025 | |||
| Request Teleconference | Teleconference Phone #: | ||
| Video Teleconference | (602) 712-7046 | ||
| 2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
| 9/25/2025 2:11:04 PM | Tricia Brown | (602) 712-7046 | 205 S 17TH AVE, , 614E |
| 6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
| SR 303L - ESTRELLA PARKWAY | DESIGN NEW FREEWAY | BK1R | ||||
| 9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
| Phoenix | 30 | Maricopa | 98.3 | F086001D | 3.4 | 030-C(003)T |
| 16. Original Program Budget: $39,350,000 | 17. Original Program Item #: 104980 |
| Project Budget | Project Budget | Project Budget |
| 18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
| $39,350,000 | $0 (0%) | $39,350,000 |
| Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
| 19. Current Approved: | 19a. New Project/Change Request: | |
| $ 24480 Item #:104980 (NHPP $24,479,670) FY:0 FundSRC: Desc: | ||
| Current Approved | New Project/Change Request | |||
| 21. Fiscal Year: | 21a. Fiscal Year: | |||
| 22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
| 23. Bid Adv Date: | 23a. Bid Adv Date: | |||
| 25. DESCRIPTION OF REQUEST |
| Establish New Project |
| 26. JUSTIFICATION |
| This project will design State Route (SR) 30 from State Route 303 to Estrella Parkway with a westbound to northbound system interchange ramp, a half traffic interchange at Sarival Avenue, and a full traffic interchange at Estrella Parkway. Funding was approved at Maricopa Association of Governments Regional Council on May 27, 2025. DOT 26-513D. Consultant: $30,000k Staff: $7,087k ICAP: $2,263k |
| 27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
| 28. OTHER ALTERNATIVES CONSIDERED |
| REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
| Establish a New Project. | Item(s) Approved. |
| Arizona Department of Transportation |