PRB Actions



Return to previous page | View Schedule | PRB Decisions | Print this page


PRB Meeting Date: 11/17/2026
Request Teleconference Teleconference Phone #:
Video Teleconference (602) 712-7046

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
11/19/2026 2:56:07 PM Tricia Brown (602) 712-7046 205 S 17TH AVE, , 614E
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
SR 303L - ESTRELLA PKWY CONSTRUCT NEW FREEWAY BK1R
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Phoenix 30 Maricopa 100.0 F086001U 0.0 030-C(003)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $21,220,000 17. Original Program Item #: 104980
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$21,220,000 $0 (0%) $21,220,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 21220 Item #:104980 ($21,220,000 Prop 479 RARF 100pct) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 32 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 6/30/2032 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Establish utility project.
26. JUSTIFICATION
This request will fund utility relocations needed to move existing Buckeye Water Conservation and Drainage District, and Roosevelt Irrigation District facilities outside of the proposed roadway limits. ICAP is included in this request. MAG TIP ID DOT26-513R
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Establish a New Project. Item(s) Approved.


PRB Meeting Date: 10/20/2026
Request Teleconference Teleconference Phone #:
Video Teleconference (602) 712-7046

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
10/26/2026 1:58:08 PM Tricia Brown (602) 712-7046 205 S 17TH AVE, , 614E
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
SR 303L - ESTRELLA PKWY CONSTRUCT NEW FREEWAY BK1R
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Phoenix 30 Maricopa 100.0 F086001U 0.0 030-C(003)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $68,965,000,000 17. Original Program Item #: 104980
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$68,965,000,000 $0 (0%) $68,965,000,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 48276 Item #:104980 ($48,275,500 Prop 479 RARF 100pct) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 32 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 6/30/2032 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Establish utility project.
26. JUSTIFICATION
This request will fund utility relocations needed to move existing Western Area Power Administration, Arizona Public Service, Salt River Project, Buckeye Water Conservation and Drainage District, and Roosevelt Irrigation District facilities outside of the proposed roadway limits. MAG TIP ID DOT26-513R
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Establish a New Project. Request Withdrawn.


PRB Meeting Date: 10/20/2026
Request Teleconference Teleconference Phone #:
Video Teleconference (602) 712-7046

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
10/26/2026 1:48:59 PM Tricia Brown (602) 712-7046 205 S 17TH AVE, , 614E
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
SR 303L - ESTRELLA PKWY CONSTRUCT NEW FREEWAY BK1R
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Phoenix 30 Maricopa 100.0 F086001R 0.0 030-C(003)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $22,380,000 17. Original Program Item #: 104980
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$22,380,000 $0 (0%) $22,380,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 6714 Item #:104980 ($6,714,099.60 NHPP) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 32 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 6/30/2032 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Establish right of way project.
26. JUSTIFICATION
This request will fund the acquisition of permanent right of way and easements needed for utility relocations. ICAP is included. Environmental clearance was issued in November 2018 for H6870 and in November 2019 for H6876. MAG TIP ID DOT26-513R
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Establish a New Project. Request Withdrawn.


PRB Meeting Date: 4/21/2026
Request Teleconference Teleconference Phone #:
Video Teleconference (602) 712-7046

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
5/12/2026 10:30:15 AM Tricia Brown (602) 712-7046 205 S 17TH AVE, , 614E
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
SR 303L - ESTRELLA PKWY CONSTRUCT NEW FREEWAY BK1R
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Phoenix 30 Maricopa 0.0 F086001R 0.0 030-C(003)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $88,470,000 17. Original Program Item #: 104980
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$88,470,000 $0 (0%) $88,470,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 68776 Item #:104980 (NHPP $68,776,045) FY:0 FundSRC: Desc: $ -19694 Item #:49926 (RARF ($19,694,011)) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 26 21a. Fiscal Year: 27  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Defer to FY 2027.
26. JUSTIFICATION
This project was kicked off for final design in March 2026 and additional time is needed to determine the right of way and utility relocation limits which will extend beyond the end of this fiscal year. This request is contingent on MAG Regional Council approval in May 2026. MAG TIP ID DOT26-513R
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Establish a New Project. Item(s) Approved. Subject to PPAC Approval.


PRB Meeting Date: 9/23/2025
Request Teleconference Teleconference Phone #:
Video Teleconference (602) 712-7046

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
9/25/2025 2:11:04 PM Tricia Brown (602) 712-7046 205 S 17TH AVE, , 614E
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
SR 303L - ESTRELLA PARKWAY DESIGN NEW FREEWAY BK1R
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Phoenix 30 Maricopa 98.3 F086001D 3.4 030-C(003)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $39,350,000 17. Original Program Item #: 104980
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$39,350,000 $0 (0%) $39,350,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 24480 Item #:104980 (NHPP $24,479,670) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Establish New Project
26. JUSTIFICATION
This project will design State Route (SR) 30 from State Route 303 to Estrella Parkway with a westbound to northbound system interchange ramp, a half traffic interchange at Sarival Avenue, and a full traffic interchange at Estrella Parkway. Funding was approved at Maricopa Association of Governments Regional Council on May 27, 2025. DOT 26-513D. Consultant: $30,000k Staff: $7,087k ICAP: $2,263k
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Establish a New Project. Item(s) Approved.


For Project Resource Office information or questions: PRO Mailbox

Arizona Department of Transportation