PRB Actions |
| Return to previous page | View Schedule | PRB Decisions | Print this page |
| PRB Meeting Date: 4/14/2026 | |||
| Request Teleconference | Teleconference Phone #: | ||
| Video Teleconference | |||
| 2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
| 5/11/2026 1:47:41 PM | Sandy Thoms | , , |
| 6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
| LAKE PLEASANT PARKWAY - 51ST AVE | GENERAL PURPOSE LANE & TI | BH1Q | ||||
| 9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
| Phoenix | 303L | Maricopa | 131.6 | F056101C | 5.1 | 303-A(229)T |
| 16. Original Program Budget: $71,261,000 | 17. Original Program Item #: 103444 |
| Project Budget | Project Budget | Project Budget |
| 18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
| $71,261,000 | $0 (0%) | $71,261,000 |
| Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
| 19. Current Approved: | 19a. New Project/Change Request: | 23-0009542, 23-0009567 |
| $ 51009 Item #:103444 (NHPP $51,008,760) FY:0 FundSRC: Desc: | $ 51009 Item #:49827 (NHPP $51,008,760) FY:0 FundSRC: Desc: | |
| Current Approved | New Project/Change Request | |||
| 21. Fiscal Year: | 26 | 21a. Fiscal Year: | 27 | |
| 22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
| 23. Bid Adv Date: | 6/28/2026 | 23a. Bid Adv Date: | ||
| 25. DESCRIPTION OF REQUEST |
| Change Project Schedule. |
| 26. JUSTIFICATION |
| This request is to move construction funding from Q4 of FY26 to Q1 of FY27. MAG will be moving the funding to facilitate timing of construction with an adjacent project. Contingent upon approval by the MAG Regional Council on May 27, 2026. |
| 27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
| 28. OTHER ALTERNATIVES CONSIDERED |
| REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
| Change in FY. | Item(s) Approved. Subject to PPAC Approval. |
| PRB Meeting Date: 4/15/2025 | |||
| Request Teleconference | Teleconference Phone #: | ||
| Video Teleconference | |||
| 2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
| 4/17/2025 1:26:56 PM | Sandy Thoms | , , |
| 6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
| LAKE PLEASANT PARKWAY - 51ST AVE | GENERAL PURPOSE LANE & TI | BH1Q | ||||
| 9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
| Phoenix | 303L | Maricopa | 131.6 | F056101R | 5.1 | 303-A(229)T |
| 16. Original Program Budget: $500,000 | 17. Original Program Item #: 103444 |
| Project Budget | Project Budget | Project Budget |
| 18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
| $500,000 | ($500,000) (0%) | $0 |
| Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
| 19. Current Approved: | 19a. New Project/Change Request: | |
| $ 471 Item #:103444 (NHPP) FY:0 FundSRC: Desc: | $ -29 Item #:49925 (RARF Match) FY:0 FundSRC: Desc: | |
| Current Approved | New Project/Change Request | |||
| 21. Fiscal Year: | 21a. Fiscal Year: | |||
| 22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
| 23. Bid Adv Date: | 23a. Bid Adv Date: | |||
| 25. DESCRIPTION OF REQUEST |
| Delete subphase |
| 26. JUSTIFICATION |
| This request is to delete the 01R subphase to this project that will add a GP lane to SR 303L from Lake Pleasant Pkwy to 51st Ave. No new ROW or TCEs will be required. |
| 27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
| 28. OTHER ALTERNATIVES CONSIDERED |
| REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
| Delete Project. | Item(s) Approved. |
| PRB Meeting Date: 9/13/2022 | |||
| Request Teleconference | Teleconference Phone #: | ||
| Video Teleconference | |||
| 2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
| 9/16/2022 3:27:21 PM | Kirstin Huston | (602) 712-2167 | 205 S 17th Ave |
| 6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
| LAKE PLEASANT PARKWAY - 51ST AVE | GENERAL PURPOSE LANE & TI | BH1Q | ||||
| 9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
| Phoenix | 303L | Maricopa | 131.6 | F056101D | 5.1 | 303-A(229)T |
| 16. Original Program Budget: $4,000,000 | 17. Original Program Item #: 103444 |
| Project Budget | Project Budget | Project Budget |
| 18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
| $4,000,000 | $0 (0%) | $4,000,000 |
| Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
| 19. Current Approved: | 19a. New Project/Change Request: | |
| $ 4000 Item #:DT55350 (HB 2858, Sect 8 FY 23) FY:0 FundSRC: Desc: | ||
| Current Approved | New Project/Change Request | |||
| 21. Fiscal Year: | 21a. Fiscal Year: | |||
| 22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
| 23. Bid Adv Date: | 23a. Bid Adv Date: | |||
| 25. DESCRIPTION OF REQUEST |
| Establish new project. |
| 26. JUSTIFICATION |
| This project will design a third general purpose lane on State Route (SR) 303 in each direction from Lake Pleasant Parkway to 51st Avenue, and TI at 67th Avenue. Consultant $3,250K Staff: $370K ICAP: $380K |
| 27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
| 28. OTHER ALTERNATIVES CONSIDERED |
| REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
| Establish a New Project. | Item(s) Approved. |
| Arizona Department of Transportation |