PRB Actions |
| Return to previous page | View Schedule | PRB Decisions | Print this page |
| PRB Meeting Date: 4/15/2025 | |||
| Request Teleconference | Teleconference Phone #: | ||
| Video Teleconference | |||
| 2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
| 4/17/2025 1:26:56 PM | Sandy Thoms | , , |
| 6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
| LAKE PLEASANT PARKWAY - 51ST AVE | GENERAL PURPOSE LANE & TI | BH1Q | ||||
| 9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
| Phoenix | 303L | Maricopa | 131.6 | F056101R | 5.1 | 303-A(229)T |
| 16. Original Program Budget: $500,000 | 17. Original Program Item #: 103444 |
| Project Budget | Project Budget | Project Budget |
| 18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
| $500,000 | ($500,000) (0%) | $0 |
| Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
| 19. Current Approved: | 19a. New Project/Change Request: | |
| $ 471 Item #:103444 (NHPP) FY:0 FundSRC: Desc: | $ -29 Item #:49925 (RARF Match) FY:0 FundSRC: Desc: | |
| Current Approved | New Project/Change Request | |||
| 21. Fiscal Year: | 21a. Fiscal Year: | |||
| 22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
| 23. Bid Adv Date: | 23a. Bid Adv Date: | |||
| 25. DESCRIPTION OF REQUEST |
| Delete subphase |
| 26. JUSTIFICATION |
| This request is to delete the 01R subphase to this project that will add a GP lane to SR 303L from Lake Pleasant Pkwy to 51st Ave. No new ROW or TCEs will be required. |
| 27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
| 28. OTHER ALTERNATIVES CONSIDERED |
| REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
| Delete Project. | Item(s) Approved. |
| PRB Meeting Date: 9/13/2022 | |||
| Request Teleconference | Teleconference Phone #: | ||
| Video Teleconference | |||
| 2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
| 9/16/2022 3:27:21 PM | Kirstin Huston | (602) 712-2167 | 205 S 17th Ave |
| 6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
| LAKE PLEASANT PARKWAY - 51ST AVE | GENERAL PURPOSE LANE & TI | BH1Q | ||||
| 9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
| Phoenix | 303L | Maricopa | 131.6 | F056101D | 5.1 | 303-A(229)T |
| 16. Original Program Budget: $4,000,000 | 17. Original Program Item #: 103444 |
| Project Budget | Project Budget | Project Budget |
| 18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
| $4,000,000 | $0 (0%) | $4,000,000 |
| Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
| 19. Current Approved: | 19a. New Project/Change Request: | |
| $ 4000 Item #:DT55350 (HB 2858, Sect 8 FY 23) FY:0 FundSRC: Desc: | ||
| Current Approved | New Project/Change Request | |||
| 21. Fiscal Year: | 21a. Fiscal Year: | |||
| 22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
| 23. Bid Adv Date: | 23a. Bid Adv Date: | |||
| 25. DESCRIPTION OF REQUEST |
| Establish new project. |
| 26. JUSTIFICATION |
| This project will design a third general purpose lane on State Route (SR) 303 in each direction from Lake Pleasant Parkway to 51st Avenue, and TI at 67th Avenue. Consultant $3,250K Staff: $370K ICAP: $380K |
| 27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
| 28. OTHER ALTERNATIVES CONSIDERED |
| REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
| Establish a New Project. | Item(s) Approved. |
| Arizona Department of Transportation |