PRB Actions



Return to previous page | View Schedule | PRB Decisions | Print this page


PRB Meeting Date: 9/26/2023
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
9/28/2023 11:52:40 AM Dana Cherry (602) 712-7030 205 S 17th Ave, , 614E
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
CITY OF PHOENIX; 13 LOCATIONS POSITIVE OFFSETS W/ FLASHING YELLOW ARROWS BC1Q
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Phoenix 0000 Maricopa PHX T039601C 0.0 HSIPPHX-0(371)D
PROJECT REQUEST SUMMARY
16. Original Program Budget: $2,527,000 17. Original Program Item #: 101881
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$2,527,000 $0 (0%) $2,527,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 2527 Item #:101881 (100pct HSIP ) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 25 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Change of Scope Change project Name
26. JUSTIFICATION
The City of Phoenix has requested a change in scope to reduce the number of intersection upgrades from 13 to 5. Due to overlapping projects and recent construction cost escalations, the city is requesting a reduction in scope to align with the available funding. Change project name to , "VARIOUS LOCATIONS, CITY OF PHOENIX".
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Change in Project Name/Location. Change in Scope. Item(s) Approved.


For Project Resource Office information or questions: PRO Mailbox

Arizona Department of Transportation