PRB Actions



Return to previous page | View Schedule | PRB Decisions | Print this page


PRB Meeting Date: 11/18/2025
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
1/8/2026 11:11:37 AM Pei-jung Li (602) 712-8708 205 S 17TH AVE, , 605E
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
N of Saddlebrooke Blvd Install DMS SIGNS AS1R
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Tucson 77 Pinal 89.5 F088001D 0.1 077-A(0)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $200,000 17. Original Program Item #: 105022
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$200,000 $0 (0%) $200,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 200 Item #:105022 (.) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 29 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Establish Design Project.
26. JUSTIFICATION
This project will install DMS and CCTV on SR 77 MP 89.5 to support effective detouring and traffic-incident management. These enhancements will improve real-time monitoring, traveler information, and overall operational improvements. Project name changed from Point location on SR 77 near MP 88 to N of Saddlebrooke Blvd. Staff - 157K Consultant - 31K ICAP - 12K
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Item(s) Approved.


For Project Resource Office information or questions: PRO Mailbox

Arizona Department of Transportation