PRB Meeting Date: 12/12/2023
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
12/14/2023 2:07:15 PM Trent Kelso (602) 723-8313 205 S 17th Ave, 295., 614E
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
GILA RIVER BRIDGE BRIDGE REPLACEMENT AL1P
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Tucson 10 Pinal 173.1 F027001D 2.5 010-C(224)S
PROJECT REQUEST SUMMARY
16. Original Program Budget: $2,600,000 17. Original Program Item #: 101235
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$2,600,000 $33,000 (0%) $2,633,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 2600 Item #:76219 ( ) FY:0 FundSRC: Desc: $ 33 Item #: 76224 (BRIDGE REPLACEMENT & REHABILITATION ) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 23 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 7/7/2023 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Increase Budget
26. JUSTIFICATION
Project has been advertised for bids but additional work is necessary to prepare addendums and answer bidding questions. Included is additional time for C&S, roadway, traffic, bridge, and PM coordination to get through the bidding process. Funding will also cover outstanding payroll and ICAP rejects. Staff $22K Consultant $5K ICAP $6K
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Item(s) Approved.


PRB Meeting Date: 5/21/2019
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
5/22/2019 3:15:09 PM Trent Kelso (602) 712-6685 205 S 17th Ave, 295., 614E
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
Gila River Bridge Bridge Replacement AL1P
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Tucson 10 Pinal 173.1 F027001D 2.5  
PROJECT REQUEST SUMMARY
16. Original Program Budget: $0 17. Original Program Item #: 101235
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$0 $2,600,000 (0%) $2,600,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 2600 Item #:76219 ( ) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Establish New Design Project
26. JUSTIFICATION
Prepare scoping and final design documents to replace the EB and WB Gila River Bridges on I-10, structure numbers #1085 and #1086. Work will include a project assessment, NEPA document, and Final Design documents. Work will be performed by staff and supplemented with consultants for environmental, compliance review, and river hydrology and hydraulics. Staff $2,018K Consultant $345K ICAP $237K
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Establish a New Project. Item(s) Approved. Subject to PPAC Approval.


For Project Resource Office information or questions: PRO Mailbox