PRB Meeting Date: 12/6/2022
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
12/8/2022 12:17:08 PM Thomas Oreilly (602) 712-2587 205 S 17th Ave, 293, 614E
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
I-19 - PENA BLANCA LAKE PAVEMENT REHABILITATION AJ1Q
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Tucson 289 Santa Cruz 0.0 F057601D 10.8 289-A(200)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $511,000 17. Original Program Item #: 103125
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$511,000 $95,000 (0%) $606,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 511 Item #:103125 (100pct State) FY:0 FundSRC: Desc: $ 95 Item #:70023 (100pct State) FY:2023 FundSRC:. Desc:ENGINEERING SUPPORT  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Establish design project.
26. JUSTIFICATION
This request is to establish a design project for a pavement rehabilitation project. Staff = $114K Consultant = $434K ICAP = $58K
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Establish a New Project. Item(s) Approved.


For Project Resource Office information or questions: PRO Mailbox