12/8/2022 12:17:08 PM | Thomas Oreilly | (602) 712-2587 | 205 S 17th Ave, 293, 614E |
6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
I-19 - PENA BLANCA LAKE | PAVEMENT REHABILITATION | AJ1Q | ||||
9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
Tucson | 289 | Santa Cruz | 0.0 | F057601D | 10.8 | 289-A(200)T |
16. Original Program Budget: $511,000 | 17. Original Program Item #: 103125 |
Project Budget | Project Budget | Project Budget |
18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
$511,000 | $95,000 (0%) | $606,000 |
Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
19. Current Approved: | 19a. New Project/Change Request: | |
$ 511 Item #:103125 (100pct State) FY:0 FundSRC: Desc: | $ 95 Item #:70023 (100pct State) FY:2023 FundSRC:. Desc:ENGINEERING SUPPORT |
Current Approved | New Project/Change Request | |||
21. Fiscal Year: | 21a. Fiscal Year: | |||
22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
23. Bid Adv Date: | 23a. Bid Adv Date: |
25. DESCRIPTION OF REQUEST |
Establish design project. |
26. JUSTIFICATION |
This request is to establish a design project for a pavement rehabilitation project. Staff = $114K Consultant = $434K ICAP = $58K |
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
28. OTHER ALTERNATIVES CONSIDERED |
REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
Establish a New Project. | Item(s) Approved. |