PRB Actions



Return to previous page | View Schedule | PRB Decisions | Print this page


PRB Meeting Date: 4/26/2022
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
3/23/2023 9:05:53 AM Judah Cain , ,
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
IR34 & IR42, TOHONO O`ODHAM NATION SAFETY IMPROVEMENTS AG1P
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Tucson 0000 Pima ITO T026401C 9.0 HSIPITO-0(211)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $0 17. Original Program Item #: 101215
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$0 $752,000 (0%) $752,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request: 19-0007519-I
$ 752 Item #:70122 ( ) FY:2022 FundSRC:. Desc:MODERNIZATION  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year: 22  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date: 6/24/2022

25. DESCRIPTION OF REQUEST
Establish construction project.
26. JUSTIFICATION
This request is to establish a construction project that will install traffic safety improvements on IR34 and IR42 for the Tohono O`odham Nation. This local agency project is fully funded with High Risk Rural Road (HRRR) apportionment from the Highway Safety Improvement Program (HSIP).
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Establish a New Project. Item(s) Approved. Subject to PPAC Approval.


PRB Meeting Date: 4/20/2021
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
6/4/2021 10:10:37 AM Judah Cain , ,
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
IR34 & IR42, TOHONO O`ODHAM NATION SAFETY IMPROVEMENTS AG1P
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Tucson 0000 Pima ITO T026401D 9.0 HSIPITO-0(211)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $0 17. Original Program Item #: 101215
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$0 $200,000 (0%) $200,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request: 19-0007519-I
$ 200 Item #:70121 (.) FY:2021 FundSRC:. Desc:MODERNIZATION  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Establish New Project.
26. JUSTIFICATION
The Intergovernmental Agreement of the subject Highway Safety Improvement Program (HRRR) project has been executed. The project consists of upgrading 4-inch wide painted centerline and edge line pavement markings to 6-inch wide thermoplastic edge lines and 4-inch wide thermoplastic centerlines and installing raised pavement markers along the centerline, installing stop signs, curve warning signs, and chevrons where needed and installing �Do Not Enter When Flooded� and depth gauge signs at wash crossings. Additional work includes grounding in centerline rumble strips and installing flexible delineators. HSIP funding will be used for the ADOT PDA Fee. Consultant - $170K ADOT PDA Fee - $30K
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Establish a New Project. Item(s) Approved. Subject to PPAC Approval.


PRB Meeting Date: 5/21/2019
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
5/22/2019 2:37:00 PM Mohammad Zaid (602) 712-8467 1611 W Jackson St, ,
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
IR34 & IR42, Tohono O`odham Nation SAFETY IMPROVEMENTS AG1P
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Tucson 0000 Pima 0.0 T022301D 9.0 ITO-0(210)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $0 17. Original Program Item #: 101215
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$0 $200,000 (0%) $200,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 200 Item #:70119 ( ) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Establish a new project
26. JUSTIFICATION
The Tohono O`odham Nation (TON) has received HSIP eligibility for safety improvements phase 4. On IR 34 from IR 15 to end of pavements, approximately 5 miles, install centerline edge line pavement markings and centerline Raised Pavement Markers (RPMs)and curve warning signs. On IR 42 from IR44 to Standfield Road, approximately 4 miles, install new thermoplastic striping, new signage and rumble strips. Staff $38K Consultant $162K
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Establish a New Project. Item(s) Approved. Subject to PPAC Approval.


For Project Resource Office information or questions: PRO Mailbox

Arizona Department of Transportation