PRB Meeting Date: 4/26/2022 | |||
Request Teleconference | Teleconference Phone #: | ||
Video Teleconference | |||
2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
3/23/2023 9:05:53 AM | Judah Cain | , , |
6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
IR34 & IR42, TOHONO O`ODHAM NATION | SAFETY IMPROVEMENTS | AG1P | ||||
9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
Tucson | 0000 | Pima | ITO | T026401C | 9.0 | HSIPITO-0(211)T |
16. Original Program Budget: $0 | 17. Original Program Item #: 101215 |
Project Budget | Project Budget | Project Budget |
18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
$0 | $752,000 (0%) | $752,000 |
Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
19. Current Approved: | 19a. New Project/Change Request: | 19-0007519-I |
$ 752 Item #:70122 ( ) FY:2022 FundSRC:. Desc:MODERNIZATION |
Current Approved | New Project/Change Request | |||
21. Fiscal Year: | 21a. Fiscal Year: | 22 | ||
22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
23. Bid Adv Date: | 23a. Bid Adv Date: | 6/24/2022 |
25. DESCRIPTION OF REQUEST |
Establish construction project. |
26. JUSTIFICATION |
This request is to establish a construction project that will install traffic safety improvements on IR34 and IR42 for the Tohono O`odham Nation. This local agency project is fully funded with High Risk Rural Road (HRRR) apportionment from the Highway Safety Improvement Program (HSIP). |
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
28. OTHER ALTERNATIVES CONSIDERED |
REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
Establish a New Project. | Item(s) Approved. Subject to PPAC Approval. |
PRB Meeting Date: 4/20/2021 | |||
Request Teleconference | Teleconference Phone #: | ||
Video Teleconference | |||
2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
6/4/2021 10:10:37 AM | Judah Cain | , , |
6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
IR34 & IR42, TOHONO O`ODHAM NATION | SAFETY IMPROVEMENTS | AG1P | ||||
9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
Tucson | 0000 | Pima | ITO | T026401D | 9.0 | HSIPITO-0(211)T |
16. Original Program Budget: $0 | 17. Original Program Item #: 101215 |
Project Budget | Project Budget | Project Budget |
18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
$0 | $200,000 (0%) | $200,000 |
Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
19. Current Approved: | 19a. New Project/Change Request: | 19-0007519-I |
$ 200 Item #:70121 (.) FY:2021 FundSRC:. Desc:MODERNIZATION |
Current Approved | New Project/Change Request | |||
21. Fiscal Year: | 21a. Fiscal Year: | |||
22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
23. Bid Adv Date: | 23a. Bid Adv Date: |
25. DESCRIPTION OF REQUEST |
Establish New Project. |
26. JUSTIFICATION |
The Intergovernmental Agreement of the subject Highway Safety Improvement Program (HRRR) project has been executed. The project consists of upgrading 4-inch wide painted centerline and edge line pavement markings to 6-inch wide thermoplastic edge lines and 4-inch wide thermoplastic centerlines and installing raised pavement markers along the centerline, installing stop signs, curve warning signs, and chevrons where needed and installing �Do Not Enter When Flooded� and depth gauge signs at wash crossings. Additional work includes grounding in centerline rumble strips and installing flexible delineators. HSIP funding will be used for the ADOT PDA Fee. Consultant - $170K ADOT PDA Fee - $30K |
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
28. OTHER ALTERNATIVES CONSIDERED |
REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
Establish a New Project. | Item(s) Approved. Subject to PPAC Approval. |
PRB Meeting Date: 5/21/2019 | |||
Request Teleconference | Teleconference Phone #: | ||
Video Teleconference | |||
2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
5/22/2019 2:37:00 PM | Mohammad Zaid | (602) 712-8467 | 1611 W Jackson St, , |
6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
IR34 & IR42, Tohono O`odham Nation | SAFETY IMPROVEMENTS | AG1P | ||||
9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
Tucson | 0000 | Pima | 0.0 | T022301D | 9.0 | ITO-0(210)T |
16. Original Program Budget: $0 | 17. Original Program Item #: 101215 |
Project Budget | Project Budget | Project Budget |
18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
$0 | $200,000 (0%) | $200,000 |
Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
19. Current Approved: | 19a. New Project/Change Request: | |
$ 200 Item #:70119 ( ) FY:0 FundSRC: Desc: |
Current Approved | New Project/Change Request | |||
21. Fiscal Year: | 21a. Fiscal Year: | |||
22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
23. Bid Adv Date: | 23a. Bid Adv Date: |
25. DESCRIPTION OF REQUEST |
Establish a new project |
26. JUSTIFICATION |
The Tohono O`odham Nation (TON) has received HSIP eligibility for safety improvements phase 4. On IR 34 from IR 15 to end of pavements, approximately 5 miles, install centerline edge line pavement markings and centerline Raised Pavement Markers (RPMs)and curve warning signs. On IR 42 from IR44 to Standfield Road, approximately 4 miles, install new thermoplastic striping, new signage and rumble strips. Staff $38K Consultant $162K |
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
28. OTHER ALTERNATIVES CONSIDERED |
REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
Establish a New Project. | Item(s) Approved. Subject to PPAC Approval. |
Arizona Department of Transportation |