PRB Actions |
| Return to previous page | View Schedule | PRB Decisions | Print this page |
| PRB Meeting Date: 12/23/2025 | |||
| Request Teleconference | Teleconference Phone #: | ||
| Video Teleconference | |||
| 2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
| 12/23/2025 3:30:21 PM | Michelle Medina | (602) 712-6530 | 205 S 17TH AVE, , |
| 6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
| MP 188 - TURPENTINE HILL | ROCKFALL MITIGATION & SHOULDER REHABILITATION | AF1R | ||||
| 9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
| Flagstaff | 40 | Coconino | 188.0 | F089601L | 1.0 | 040-C(237)T |
| 16. Original Program Budget: $500,000 | 17. Original Program Item #: 105021 |
| Project Budget | Project Budget | Project Budget |
| 18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
| $500,000 | ($295,000) (0%) | $205,000 |
| Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
| 19. Current Approved: | 19a. New Project/Change Request: | |
| $ 500 Item #:105021 ( ) FY:0 FundSRC: Desc: | $ -295 Item #:70726 (.) FY:0 FundSRC: Desc: | |
| Current Approved | New Project/Change Request | |||
| 21. Fiscal Year: | 26 | 21a. Fiscal Year: | ||
| 22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
| 23. Bid Adv Date: | 23a. Bid Adv Date: | |||
| 25. DESCRIPTION OF REQUEST |
| Establish Scoping Project. |
| 26. JUSTIFICATION |
| This project will provide funding for the scoping phase of the I-40 rockfall mitigation project. The scope includes evaluating options to mitigate rockfall at an existing steep slope along I-40, near Flagstaff. Staff: $193K Consultant: $0 ICAP: $12K |
| 27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
| 28. OTHER ALTERNATIVES CONSIDERED |
| REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
| Establish a New Project. | Item(s) Approved. |
| PRB Meeting Date: 7/1/2025 | |||
| Request Teleconference | Teleconference Phone #: | ||
| Video Teleconference | |||
| 2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
| 7/2/2025 9:06:14 AM | Jason James | , , |
| 6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
| I-40 MP 189 - Turpentine Hill Rockfall Mitigation | Scoping | AF1R | ||||
| 9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
| Flagstaff | 40 | Coconino | 189 | _ | 1 | |
| 16. Original Program Budget: $600,000 | 17. Original Program Item #: 105021 |
| Project Budget | Project Budget | Project Budget |
| 18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
| $600,000 | $0 (0%) | $600,000 |
| Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
| 19. Current Approved: | 19a. New Project/Change Request: | |
| $ 600 Item #:105021 ( ) FY:0 FundSRC: Desc: | ||
| Current Approved | New Project/Change Request | |||
| 21. Fiscal Year: | 21a. Fiscal Year: | |||
| 22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
| 23. Bid Adv Date: | 23a. Bid Adv Date: | |||
| 25. DESCRIPTION OF REQUEST |
| Establish new project |
| 26. JUSTIFICATION |
| This is a project to rehabilitate the shoulder, widen the inside shoulder, and mitigate rockfall on I-40 near MP 189. |
| 27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
| 28. OTHER ALTERNATIVES CONSIDERED |
| REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
| Establish a New Project. | Request Withdrawn. |