PRB Meeting Date: 4/23/2024 | |||
Request Teleconference | Teleconference Phone #: | ||
Video Teleconference | |||
2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
4/25/2024 11:43:49 AM | Pedram Shafieian | (602) 712-8166 | 205 S 17th Ave, , 068R |
6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
TYSON ST - N. OF QUARTZSITE | PAVEMENT REHABILITATION | AF1Q | ||||
9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
Yuma | 95 | La Paz | 109.1 | F059101C | 6.9 | NHPP095-C(227)T |
16. Original Program Budget: $12,514,000 | 17. Original Program Item #: 103129 |
Project Budget | Project Budget | Project Budget |
18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
$12,514,000 | $0 (0%) | $12,514,000 |
Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
19. Current Approved: | 19a. New Project/Change Request: | |
$ 11800 Item #:103129 (NHPP) FY:0 FundSRC: Desc: | $ 12514 Item #:72324 (.) FY:2024 FundSRC:. Desc:CONTINGENCY |
Current Approved | New Project/Change Request | |||
21. Fiscal Year: | 25 | 21a. Fiscal Year: | 24 | |
22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
23. Bid Adv Date: | 7/23/2024 | 23a. Bid Adv Date: | 6/28/2024 |
25. DESCRIPTION OF REQUEST |
Advance construction project to FY24 |
26. JUSTIFICATION |
The project is road rehabilitation of State Route 95 from Milepost 109.05 to Milepost 116. Funds are available to advertise the project in FY24. |
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
28. OTHER ALTERNATIVES CONSIDERED |
REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
Change in FY. Change in Schedule. | Item(s) Approved. Subject to PPAC Approval. |
PRB Meeting Date: 2/28/2023 | |||
Request Teleconference | Teleconference Phone #: | ||
Video Teleconference | |||
2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
3/1/2023 3:02:14 PM | Pedram Shafieian | (602) 712-8166 | 205 S 17th Ave, , 068R |
6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
TYSON ST - N. OF QUARTZSITE | PAVEMENT REHABILITATION | AF1Q | ||||
9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
Yuma | 95 | La Paz | 109.05 | F059101D | 6.95 |
16. Original Program Budget: $557,000 | 17. Original Program Item #: 103129 |
Project Budget | Project Budget | Project Budget |
18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
$557,000 | ($29,000) (0%) | $528,000 |
Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
19. Current Approved: | 19a. New Project/Change Request: | |
$ 557 Item #:103129 (State 100pct) FY:0 FundSRC: Desc: | $ -29 Item #:70023 (State 100pct) FY:2023 FundSRC:. Desc:ENGINEERING SUPPORT |
Current Approved | New Project/Change Request | |||
21. Fiscal Year: | 21a. Fiscal Year: | |||
22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
23. Bid Adv Date: | 23a. Bid Adv Date: |
25. DESCRIPTION OF REQUEST |
Establish new project |
26. JUSTIFICATION |
The project is road rehabilitation of State Route 95 from Milepost 109.05 to Milepost 116. Staff $478K ICAP: $50K |
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
28. OTHER ALTERNATIVES CONSIDERED |
REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
Establish a New Project. | Item(s) Approved. |