![]() |
PRB Actions |
| Return to previous page | View Schedule | PRB Decisions | Print this page |
| PRB Meeting Date: 11/25/2025 | |||
| Request Teleconference | Teleconference Phone #: | ||
| Video Teleconference | (602) 712-7046 | ||
| 2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
| 11/26/2025 2:25:58 PM | Tricia Brown | (602) 712-7046 | 205 S 17TH AVE, , 614E |
| 6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
| VISTA ROYALE | CONSTRUCT TO 4 LANES DIVIDED | AE1Q | ||||
| 9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
| Kingman | 93 | Yavapai | 190.5 | F073801C | 3.0 | 093-B(230)T |
| 16. Original Program Budget: $58,861,000 | 17. Original Program Item #: 103024 |
| Project Budget | Project Budget | Project Budget |
| 18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
| $58,861,000 | $9,239,000 (0%) | $68,100,000 |
| Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
| 19. Current Approved: | 19a. New Project/Change Request: | |
| $ 26000 Item #:103024 (INFRA Grant) FY:0 FundSRC: Desc: | $ 9239 Item #:72326 ($9,239,438) FY:0 FundSRC: Desc: | |
| Current Approved | New Project/Change Request | |||
| 21. Fiscal Year: | 26 | 21a. Fiscal Year: | ||
| 22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
| 23. Bid Adv Date: | 6/30/2026 | 23a. Bid Adv Date: | ||
| 25. DESCRIPTION OF REQUEST |
| Add Scope and Budget from F012501C. Change Project Limits. Change Project Name. |
| 26. JUSTIFICATION |
| Projects F0125, US 93 Wickenburg Ranch Way - SR 89 and F0738 Vista Royale, will both convert existing US 93 from a two-lane roadway to a 4-lane divided highway. The project are adjacent to each other and combining the scope of the two projects will facilitate easier construction management and lower construction costs. Request to add scope and budget from F012501C. Request to change the project length to 4.5 miles; MP 190 to 194.5 Request to change the project name to: Wickenburg Ranch Way to Vista Royale |
| 27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
| 28. OTHER ALTERNATIVES CONSIDERED |
| REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
| Change in Project Name/Location. Change in Scope. | Item(s) Approved. |
| PRB Meeting Date: 4/8/2025 | |||
| Request Teleconference | Teleconference Phone #: | ||
| Video Teleconference | (602) 712-7046 | ||
| 2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
| 4/10/2025 10:34:46 AM | Tricia Brown | (602) 712-7046 | 205 S 17TH AVE, , 614E |
| 6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
| VISTA ROYALE | CONSTRUCT TO 4 LANES DIVIDED | AE1Q | ||||
| 9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
| Kingman | 93 | Yavapai | 190.5 | F073801R | 3.0 | 093-B(230)T |
| 16. Original Program Budget: $0 | 17. Original Program Item #: 103024 |
| Project Budget | Project Budget | Project Budget |
| 18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
| $0 | $47,000,000 (0%) | $47,000,000 |
| Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
| 19. Current Approved: | 19a. New Project/Change Request: | |
| $ 393 Item #:71025 (Right of Way) FY:0 FundSRC: Desc: | ||
| Current Approved | New Project/Change Request | |||
| 21. Fiscal Year: | 21a. Fiscal Year: | |||
| 22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
| 23. Bid Adv Date: | 23a. Bid Adv Date: | |||
| 25. DESCRIPTION OF REQUEST |
| Establish Right of Way Subphase |
| 26. JUSTIFICATION |
| Funding is needed for the acquisition of right of way and temporary construction easements (TCEs) for new northbound mainline, driveway reconstruction, pipe culvert installation, drainage ditch side slopes, and intersection improvements as outlined in the Final Design Concept Report approved in September 2006. A Finding of No Significant Impact (FONSI) was approved by the Federal Highway Administration on April 18, 2005. R/W Acquisition: $43,558k ICAP: $3,442k |
| 27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
| 28. OTHER ALTERNATIVES CONSIDERED |
| REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
| Establish a New Project. | Item(s) Approved. Subject to PPAC Approval. |
| PRB Meeting Date: 3/26/2024 | |||
| Request Teleconference | Teleconference Phone #: | ||
| Video Teleconference | |||
| 2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
| 4/1/2024 2:07:23 PM | Tricia Brown | (602) 712-7046 | 205 S 17th Ave, , 614E |
| 6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
| VISTA ROYALE | CONSTRUCT TO 4 LANES DIVIDED | AE1Q | ||||
| 9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
| Kingman | 93 | Yavapai | 190.5 | F073801D | 3.0 | |
| 16. Original Program Budget: $10,500,000 | 17. Original Program Item #: 103024 |
| Project Budget | Project Budget | Project Budget |
| 18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
| $10,500,000 | $0 (0%) | $10,500,000 |
| Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
| 19. Current Approved: | 19a. New Project/Change Request: | |
| $ 10500 Item #:103024 ( ) FY:0 FundSRC: Desc: | $ -10500 Item #:79925 (.) FY:0 FundSRC: Desc: | |
| Current Approved | New Project/Change Request | |||
| 21. Fiscal Year: | 25 | 21a. Fiscal Year: | 24 | |
| 22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
| 23. Bid Adv Date: | 23a. Bid Adv Date: | |||
| 25. DESCRIPTION OF REQUEST |
| Advance Design into FY24. |
| 26. JUSTIFICATION |
| This project will reconstruct to a four lane divided highway. Design project is currently in the Five Year Program in FY25. Staff $4,485K Consultant $5,000K ICAP $1,015K |
| 27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
| 28. OTHER ALTERNATIVES CONSIDERED |
| REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
| Change in FY. | Item(s) Approved. Subject to PPAC Approval. |
| Arizona Department of Transportation |