RT CO MP TRACS D PROJECT NAME CPSID TYPE OF WORK PROJECT MANAGER BID ADV SCHEDULER
40 MO 0.1 F055701C NW CA BORDER - NEEDLE MT. ROAD ZQ1P PAVEMENT REHABILITATION SANDY THOMS
602-712-7607
6/21/2024 Lee Makler
602-712-8579
Current Program Budget $19,200,000 Program FY 24

Project Milestones
Milestone Name Date  ("A" denotes actual finish)
NTP 2023-04-06 A
Kickoff 2023-05-09 A
Stage 3 - 60% 2024-01-16 A
Stage 4 - 95% 2024-04-16 A
EPG Clearance 2024-05-25
RW Clearance 2024-04-24 A
URR Clearance 2024-05-04
Stage 5 - 100% 2024-05-18
Advertise 2024-06-22
Bids Opening 2024-08-24