Project Milestones
Milestone Name Date  ("A" denotes actual finish)
NTP 2012-07-03 A
Kickoff 2018-08-14 A
Stage 1 - 15% 2017-11-07 A
Stage 2 - 30% 2020-07-24 A
Stage 3 - 60% 2022-02-15 A
Stage 4 - 95% 2022-10-03 A
EPG Clearance 2023-04-13 A
RW Clearance 2023-05-23 A
URR Clearance 2023-03-10 A
Advertise 2023-05-31 A
Bids Opening 2023-11-17 A