RT CO MP TRACS D PROJECT NAME CPSID TYPE OF WORK PROJECT MANAGER BID ADV SCHEDULER
0000 MA GLN T037301C CL MARYLAND AVE - BETHANY HOME RD & YI1P IMPROVE SIDEWALKS & ADA RAMPS CHRIS RODRIGUEZ
602-617-9560
5/27/2026 Lee Makler
602-712-8579
Current Program Budget $5,229,000 Program FY 26

Project Milestones
Milestone Name Date  ("A" denotes actual finish)
NTP 2023-03-22 A
Stage 3 - 60% 2024-02-01 A
Stage 4 - 95% 2024-09-20 A
EPG Clearance 2024-07-02 A
RW Clearance 2026-01-16
URR Clearance 2024-12-11 A
Stage 5 - 100% 2026-01-16
Advertise 2026-05-22
Bids Opening 2026-07-18