Active Project List



Return to Project listing | Print this page

 
RT CO MP TRACS D PROJECT NAME CPSID TYPE OF WORK PROJECT MANAGER BID ADV SCHEDULER
0000 MA GLN T037301D CL MARYLAND AVE - BETHANY HOME RD & YI1P IMPROVE SIDEWALKS & ADA RAMPS CHRIS RODRIGUEZ
602-617-9560
5/27/2025 Lee Makler
602-712-8579
Current Program Budget $1,594,000 Program FY 25

Project Milestones
Milestone Name Date  ("A" denotes actual finish)
NTP 2023-03-22 A
Stage 3 - 60% 2024-02-01 A
Stage 4 - 95% 2024-09-20 A
EPG Clearance 2024-07-02 A
RW Clearance 2025-03-28
URR Clearance 2024-12-21
Stage 5 - 100% 2025-04-01
Advertise 2025-05-27
Bids Opening 2025-07-19




For Project Resource Office information or questions: PRO Mailbox