| Project Milestones | |
|---|---|
| Milestone Name | Date ("A" denotes actual finish) |
| NTP | 2023-03-22 A |
| Stage 3 - 60% | 2024-02-01 A |
| Stage 4 - 95% | 2024-09-20 A |
| EPG Clearance | 2024-07-02 A |
| RW Clearance | 2026-01-16 |
| URR Clearance | 2024-12-11 A |
| Stage 5 - 100% | 2026-01-16 |
| Advertise | 2026-05-22 |
| Bids Opening | 2026-07-18 |
| |