Active Project List |
Return to Project listing | Print this page |
Project Milestones | |
---|---|
Milestone Name | Date ("A" denotes actual finish) |
NTP | 2021-10-05 A |
Kickoff | 2021-10-29 A |
Stage 2 - 30% | 2022-08-05 A |
Stage 3 - 60% | 2022-12-23 A |
Stage 4 - 95% | 2023-03-16 A |
EPG Clearance | 2023-03-23 A |
RW Clearance | 2023-06-23 A |
URR Clearance | 2023-06-07 A |
Stage 5 - 100% | 2023-06-07 A |
Advertise | 2023-07-14 A |
Bids Opening | 2023-11-17 A |
Award Date | 2023-12-15 A |
|
Arizona Department of Transportation |