ADOTNet : Home

Active Project List



Return to Project listing | Print this page

 
RT CO MP TRACS D PROJECT NAME CPSID TYPE OF WORK PROJECT MANAGER BID ADV SCHEDULER
202L MA 50.6 F084701D CL SR 101L - I-10 YD1Q CONSTRUCT GPL PATRICK O'LESKE
602-712-7629
TBD Lee Makler
602-712-8579
Current Program Budget   Program FY 26

Project Milestones
Milestone Name Date  ("A" denotes actual finish)
NTP 2025-12-24
Kickoff 2025-12-06
Stage 2 - 30% 2025-12-24
Stage 3 - 60% 2025-12-25
Stage 4 - 95% 2026-01-15
EPG Clearance 2025-12-25
RW Clearance 2026-01-15
URR Clearance 2026-01-23
Stage 5 - 100% 2026-02-05
Advertise 2026-03-24
Bids Opening 2026-03-26




For Project Resource Office information or questions: PRO Mailbox

Arizona Department of Transportation