Active Project List |
Return to Project listing | Print this page |
Project Milestones | |
---|---|
Milestone Name | Date ("A" denotes actual finish) |
NTP | 2022-10-03 A |
Kickoff | 2022-11-04 A |
Stage 4 - 95% | 2023-01-18 A |
EPG Clearance | 2023-03-20 A |
RW Clearance | 2023-03-22 A |
URR Clearance | 2023-01-26 A |
Stage 5 - 100% | 2023-05-01 A |
Advertise | 2023-06-01 A |
Bids Opening | 2023-08-18 A |
|