Project Milestones | |
---|---|
Milestone Name | Date ("A" denotes actual finish) |
NTP | 2023-02-02 A |
Stage 3 - 60% | 2023-07-31 A |
Stage 4 - 95% | 2023-12-13 A |
EPG Clearance | 2023-10-06 A |
RW Clearance | 2023-10-25 A |
URR Clearance | 2024-05-07 |
Stage 5 - 100% | 2024-05-16 |
Advertise | 2024-06-20 |
Bids Opening | 2024-08-29 |
|