ADOTNet : Home

Active Project List



Return to Project listing | Print this page

 
RT CO MP TRACS D PROJECT NAME CPSID TYPE OF WORK PROJECT MANAGER BID ADV SCHEDULER
17 CN 252.8 F051501C NW SUNSET POINT - I-17/I-40 TI XM1P INSTALL CCTV, DMS & RWIS CHRIS MOORE
602-712-2132
1/31/2025 Lee Makler
602-712-8579
Current Program Budget $6,100,000 Program FY 25

Project Milestones
Milestone Name Date  ("A" denotes actual finish)
NTP 2022-10-19 A
Kickoff 2022-10-25 A
Stage 3 - 60% 2023-02-06 A
Stage 4 - 95% 2024-07-22 A
EPG Clearance 2024-07-22 A
RW Clearance 2024-08-30 A
URR Clearance 2024-09-23 A
Stage 5 - 100% 2024-09-23 A
Advertise 2024-12-14
Bids Opening 2025-03-22




For Project Resource Office information or questions: PRO Mailbox

Arizona Department of Transportation