| Project Milestones | |
|---|---|
| Milestone Name | Date ("A" denotes actual finish) |
| NTP | 2022-10-25 A |
| Kickoff | 2022-11-03 A |
| Stage 2 - 30% | 2023-02-28 A |
| Stage 3 - 60% | 2023-04-24 A |
| Stage 4 - 95% | 2024-03-22 A |
| EPG Clearance | 2024-06-21 A |
| RW Clearance | 2024-06-04 A |
| URR Clearance | 2024-05-29 A |
| Stage 5 - 100% | 2024-05-22 A |
| Advertise | 2024-06-27 A |
| Bids Opening | 2024-11-15 A |
| |