RT CO MP TRACS D PROJECT NAME CPSID TYPE OF WORK PROJECT MANAGER BID ADV SCHEDULER
40 CN 240.0 F084101D NC DENNISON - NAVAJO COUNTY LINE XE1Q PAVEMENT REHABILITATION TRICIA BROWN
602-712-7046
Design Lee Makler
602-712-8579
Current Program Budget $750,000 Program FY 25

Project Milestones
Milestone Name Date  ("A" denotes actual finish)
NTP 2025-11-29
Kickoff 2025-11-13
Stage 2 - 30% 2025-11-29
Stage 3 - 60% 2025-12-02
Stage 4 - 95% 2025-12-23
EPG Clearance 2025-12-02
RW Clearance 2025-12-23
URR Clearance 2025-12-31
Stage 5 - 100% 2026-01-13
Advertise 2026-02-27
Bids Opening 2026-03-03