RT CO MP TRACS D PROJECT NAME CPSID TYPE OF WORK PROJECT MANAGER BID ADV SCHEDULER
30 MA 112.2 F050101D CL 71ST AVE - SR 202L (SOUTH MOUNTAI XE1P DESIGN NEW FREEWAY INTERCHANGE RASHIDUL HAQUE
602-712-7352
Design Lee Makler
602-712-8579
Current Program Budget $25,463,000 Program FY 24

Project Milestones
Milestone Name Date  ("A" denotes actual finish)
NTP 2024-09-23 A
Kickoff 2024-10-22 A
Stage 2 - 30% 2025-07-23
Stage 3 - 60% 2026-06-06
Stage 4 - 95% 2026-07-15
EPG Clearance 2026-03-27
RW Clearance 2026-06-06
URR Clearance 2026-07-23
Stage 5 - 100% 2026-09-23
Advertise 2026-12-08
Bids Opening 2027-05-22