Milestone Name | Date ("A" denotes actual finish) |
NTP | 2024-09-23 A |
Kickoff | 2024-10-22 A |
Stage 2 - 30% | 2025-07-23 |
Stage 3 - 60% | 2026-06-06 |
Stage 4 - 95% | 2026-07-15 |
EPG Clearance | 2026-03-27 |
RW Clearance | 2026-06-06 |
URR Clearance | 2026-07-23 |
Stage 5 - 100% | 2026-09-23 |
Advertise | 2026-12-08 |
Bids Opening | 2027-05-22 |
|