ADOTNet : Home

Active Project List



Return to Project listing | Print this page

 
RT CO MP TRACS D PROJECT NAME CPSID TYPE OF WORK PROJECT MANAGER BID ADV SCHEDULER
30 MA 112.2 F050101D CL 71ST AVE - SR 202L (SOUTH MOUNTAI XE1P DESIGN NEW FREEWAY INTERCHANGE RASHIDUL HAQUE
602-712-7352
Design Lee Makler
602-712-8579
Current Program Budget $25,463,000 Program FY 24

Project Milestones
Milestone Name Date  ("A" denotes actual finish)
NTP 2023-11-02
Kickoff 2022-11-02
Stage 2 - 30% 2022-11-08
Stage 3 - 60% 2022-12-20
Stage 4 - 95% 2023-02-14
EPG Clearance 2023-02-14
RW Clearance 2023-02-21
URR Clearance 2023-02-22
Stage 5 - 100% 2023-03-07
Advertise 2025-09-13
Bids Opening 2025-10-25




For Project Resource Office information or questions: PRO Mailbox

Arizona Department of Transportation