Project Milestones | |
---|---|
Milestone Name | Date ("A" denotes actual finish) |
Stage 3 - 60% | 2023-12-06 A |
Stage 4 - 95% | 2024-02-28 A |
EPG Clearance | 2024-03-06 A |
RW Clearance | 2024-03-24 A |
URR Clearance | 2024-05-03 |
Stage 5 - 100% | 2024-04-19 |
Advertise | 2024-05-18 |
Bids Opening | 2024-07-13 |
|