ADOTNet : Home

Active Project List



Return to Project listing | Print this page

 
RT CO MP TRACS D PROJECT NAME CPSID TYPE OF WORK PROJECT MANAGER BID ADV SCHEDULER
40 AP 342.2 F075501C NE QUERINO - HAWTHORNE WR1P PAVEMENT REHABILITATION CONNIE CORVALAN
602-712-3062
TBD Lee Makler
602-712-8579
Current Program Budget $51,986,000 Program FY 28

Project Milestones
Milestone Name Date  ("A" denotes actual finish)
NTP 2024-06-11
Kickoff 2024-07-27
Stage 2 - 30% 2024-10-26
Stage 3 - 60% 2025-03-29
Stage 4 - 95% 2025-07-26
EPG Clearance 2025-07-12
RW Clearance 2025-08-23
URR Clearance 2025-08-30
Stage 5 - 100% 2025-11-15
Advertise 2025-12-18
Bids Opening 2026-01-29




For Project Resource Office information or questions: PRO Mailbox

Arizona Department of Transportation