RT CO MP TRACS D PROJECT NAME CPSID TYPE OF WORK PROJECT MANAGER BID ADV SCHEDULER
95 YV 44.1 F083201C SW IMPERIAL DAM AND ABERDEEN RD INTE WQ1Q INTERSECTION IMPROVEMENTS TRENT KELSO
602-712-6685
9/16/2025 Lee Makler
602-712-8579
Current Program Budget $35,000,000 Program FY 26

Project Milestones
Milestone Name Date  ("A" denotes actual finish)
NTP 2023-09-01 A
Kickoff 2023-10-17 A
Stage 2 - 30% 2024-02-23 A
Stage 3 - 60% 2024-06-18 A
Stage 4 - 95% 2025-06-14
EPG Clearance 2024-09-18 A
RW Clearance 2025-07-01
URR Clearance 2025-07-22
Stage 5 - 100% 2025-08-23
Advertise 2025-09-17
Bids Opening 2025-12-17




For Project Resource Office information or questions: PRO Mailbox