Project Milestones | |
---|---|
Milestone Name | Date ("A" denotes actual finish) |
NTP | 2024-01-18 A |
Stage 2 - 30% | 2024-08-30 A |
Stage 3 - 60% | 2025-01-18 |
Stage 4 - 95% | 2025-04-26 |
EPG Clearance | 2025-03-08 |
RW Clearance | 2025-05-17 |
URR Clearance | 2025-05-26 |
Stage 5 - 100% | 2026-05-09 |
Advertise | 2026-07-21 |
Bids Opening | 2026-08-18 |
Award Date | 2026-09-16 |
|